Light Commercial R410A on-off
S13-01.01.13en
7.
Test Operation
(1) The test operation must be carried out after the entire installation has been completed.
(2) Please confirm the following points before the test operation.
The indoor unit and outdoor unit are installed properly.
Tubing and wiring are correctly completed.
The refrigerant pipe system is leakage-checked.
The drainage is unimpeded.
The ground wiring is connected correctly.
The length of the tubing and the added stow capacity of the refrigerant have been recorded.
The power voltage fits the rated voltage of the air conditioner.
There is no obstacle at the outlet and inlet of the outdoor and indoor units.
The gas-side and liquid-side stop values are both opened.
The air conditioner is pre-heated by turning on the power.
(3) According to the user's requirement, install the remote controller when the remote controller's
signal can reach the indoor unit smoothly.
(4) Test operation
Set the air conditioner under the mode of "COOLING" with the remote controller, and check the following
points.
Indoor unit
Whether the switch on the remote controller works well.
Whether the buttons on the remote controller works well.
Whether the air flow louver moves normally.
Whether the room temperature is adjusted well.
Whether the indicator lights normally.
Whether the temporary buttons works well.
Whether the drainage is normal.
Whether there is vibration or abnormal noise during operation.
Outdoor unit
Whether there is vibration or abnormal noise during operation.
Whether the generated wind, noise, or
neighborhood.
Whether any of the refrigerant is leaked.
condensed of by the air conditioner have influenced your
Installation
118
Summary of Contents for SOB-50VA
Page 1: ...S13 01 01 13en Light Commercial Air Conditioner R410A ON OFF Service Manual 2013...
Page 6: ...Light Commercial R410A on off S13 01 01 13en 2 2 Outdoor Units General Information 5...
Page 48: ...Light Commercial R410A on off S13 01 01 13en 4 Service Space Indoor Units Ceiling Floor 47...
Page 62: ...Light Commercial R410A on off S13 01 01 13en SIB 50TAV SIB 60TAV Indoor Units Ceiling Floor 61...
Page 68: ...Light Commercial R410A on off S13 01 01 13en 3 Dimensions Indoor Units HSP Duct Type 67...
Page 69: ...Light Commercial R410A on off S13 01 01 13en Indoor Units HSP Duct Type 68...
Page 91: ...Light Commercial R410A on off S13 01 01 13en 5 Wiring Diagrams SOB 50VA Outdoor Units 90...
Page 92: ...Light Commercial R410A on off S13 01 01 13en SOB 60VA SOB 100YA Outdoor Units 91...
Page 93: ...Light Commercial R410A on off S13 01 01 13en SOB 140YA SOB 200YA Outdoor Units 92...