LADDER MIDWAY REST PLATFORM
INSTALLATION
1.
Establish the floor height required for the midway rest platform.
2.
Install the
angle bar 50mm
below the
established floor height. Ensure angle bar is
levelled. Angle bar requires minimum
of three
(3) M12 fixing points (not supplied).
3.
Raise the Rest platform to established floor height
and fix it into existing angle bar by using two (2)
M10x80 bolts.
4.
Fix the Rest platform into building structure by
using M12 bolts. Each angle bar requires three
(3) M12 fixing bolts.
5.
Platform is ready to install the top and bottom
ladders.
a.
Once the rest platform is secured, the bottom ladder can be put in place. The bottom ladder should extend
b.
to the top of the rest platform.
c.
The top and bottom ladder can now be assembled.
WORKING LOAD LIMIT
Recommended for single person use-150kg rated.
Support structure integrity and fixing method to be assessed and confirmed by competent person or Engineer
prior to installation.