background image

Page 5 of 6

 CAUTION

Failure to support loose receiver tube may allow it to fall, 
resulting in minor injury or property damage.

Fig. 13 - Removed receiver tube

9. Remove the receiver tube and continue to operate the 
hydraulic actuator until the pivot bushing is completely 
drawn into the receptacle.

10. Disassemble and remove the installation tool.

11. Check the spring center and readjust as needed using 
dead blow mallet. 
Fig. 14 shows a spring center of 1300 mm, for example.  

Dual tyre standard measurements: 
940mm Intra disc
960 Intra drum 

12. Check the proper orientation of the pivot bushing.
Make sure that the orientation index marked “TOP”
(in white colour for illustration purposes) faces upward 
and that the bushing position locator of the replacement 
bushing is aligned with the bushing orientation line 
drawn on the outside of the receptacle
(Fig. 15). If the replacement pivot bushing is not installed 
properly, remove and reinstall it.

Remove the pivot bushing on the opposite axle side as 
described earlier and install a replacement pivot bushing 
as outlined.

8. Operate the Hydraulic pump until the drive nut (6) 
and the pivot bushing are completely drawn into the 
receptacle (5) and the receiver tube becomes loose and 
can be removed (Fig. 13).

Fig. 14 - Checking spring center

Fig. 15 - Checking installation position

FINAL STEPS

Upon replacement of the pivot bushing, perform the 
following final steps in compliance with the relevant 
operating instructions and the associated repair and 
maintenance manual. Observe the relevant safety 
instructions and the specified tightening torques:
1. Lift the axle ensuring new wear mounts are installed. 
2. Install and slightly tighten new pivot bolts and nuts.
3. Install the shock absorber using new nuts.
4. Remove the axle supports. 
5. Apply air pressure to the air suspension system.
6. Remove the wheel chocks.
7. Adjust the ride height.
8. Check the axle alignment of the trailer.
9. Tighten the pivot bolt, referring to the appropriate 
tightening instructions and specifications on the 
following page.

Ph 03 9971 7900   ·   [email protected]    ·   2019-08   ·   SB-65

SAF-HOLLAND (Aust.) Pty. Ltd. · www.safholland.com.au

Group

Summary of Contents for 3 434 3317 00

Page 1: ... relevant operating instructions and the associated repair and maintenance manual observing the indicated safety instructions 1 Place wheel cocks in front of and behind the trailer wheels to prevent the trailer from rolling WARNING Failure to use wheel chocks might allow the vehicle to roll which could result in death or serious injury 2 Bleed all air from the air suspension system 3 Suitably supp...

Page 2: ...ntering ring faces toward the cover plate The centering ring Fig 3 of the receiver tube is used to center the receiver tube on the trailing arm receptacle When the removal tool is used the centering ring must always face toward the trailing arm receptacle Fig 3 Receiver tube with centering ring Centering Ring REMOVAL Fig 1 Identification of removal tool components Preparing the Pivot Bush Replacem...

Page 3: ...ing will reduce vehicle stability which could result in death or serious injury 3 Lubricate the Drive nut 6 and the threads on the threaded rod 4 Use standard grease 4 Insert the threaded rod end 4 of the correctly pre assembled removal tool through the hole in the pivot bushing until the centering ring of the receiver tube 5 fits the bushing receptacle Screw the drive nut 6 onto the threaded rod ...

Page 4: ...he bushing position locator of the replacement bushing must be aligned with the line on the outside of the receiver tube The orientation index marked Top must face upward as illustrated in Fig 10 If need be readjust the pivot bushing 5 Push the pivot bushing and the drive disc 6 completely into the receiver tube as shown in Fig 11 Fig 8 Lubricated receptacle Fig 9 Lubricated pivot bushing Fig 10 C...

Page 5: ... opposite axle side as described earlier and install a replacement pivot bushing as outlined 8 Operate the Hydraulic pump until the drive nut 6 and the pivot bushing are completely drawn into the receptacle 5 and the receiver tube becomes loose and can be removed Fig 13 Fig 14 Checking spring center Fig 15 Checking installation position FINAL STEPS Upon replacement of the pivot bushing perform the...

Page 6: ...onths Service Intervals for Steel Hanger Brackets First check after 5000kms Further checks every 12 months Pivot bolt Inspection torque 1 200 Nm Shock absorber bolt Inspection torque 600 Nm Tightening torques for SAF air suspension systems M12 SW19 40 Nm M16 SW24 180 Nm for steel plunger piston 80 Nm for plastic plunger piston M30 SW46 400Nm 120o Tightening torques SAF INTRA with aluminum hanger b...

Reviews: