INSTALLATION

! IMPORTANT

The centering ring of the receiver tube is used to center the receiver tube on the trailing arm receptacle. When 
the installation tool is used, the centering ring must always be positioned against the trailing arm receptacle.

Installing the Pivot Bushing

1. Lubricate the threads on the threaded rod (4).

2. Apply installation lubricant evenly to the internal 
surface of the receptacle as illustrated in Fig. 8 and to 
the external surface of the replacement pivot bushing as 
shown in Fig. 9.

3. Use installation lubricant P-80 Emulsion.

 WARNING

Failure to use proper lubricant during pivot bushing 
installation could reduce vehicle stability which could 
result in death or serious injury.

4. Insert the pivot bushing into the receiver tube end 
opposite of the centering ring. Make sure that the pivot 
bushing is properly aligned in the receiver tube using the 
bushing position locator as a reference point (Fig. 10). 
The bushing position locator of the replacement bushing 
must be aligned with the line on the outside of the 
receiver tube. The orientation index marked “Top” must 
face upward as illustrated in Fig. 10. If need be, readjust 
the pivot bushing.

5. Push the pivot bushing and the drive disc (6) 
completely into the receiver tube as shown in Fig. 11. 

Fig. 8 - Lubricated receptacle

Fig. 9 - Lubricated pivot bushing

Fig. 10 - Correctly aligned pivot bushing

Fig. 11 - Installing the drive disc

6. Insert the threaded rod (4) of the pre-assembled 
installation tool from the wheel side through the 
receptacle, making sure that the cover plate (4) is 
positioned properly against the receptacle as illustrated 
in Fig. 12.

7. Slide the receiver tube (5) over the exposed threaded 
rod (4) with the centering ring of the receiver tube 
facing toward the receptacle until the receiver tube rests 
squarely on the receptacle. Fasten the drive nut ensuring 
the drive plate is in place. 

Make sure that the line previously drawn on the external 
surface of the receptacle is aligned with the line on the 
receiver tube.

Note: Use the same tool for installation.

Fig. 12 - Correct receiver tube position

Summary of Contents for 3 434 3317 00

Page 1: ... relevant operating instructions and the associated repair and maintenance manual observing the indicated safety instructions 1 Place wheel cocks in front of and behind the trailer wheels to prevent the trailer from rolling WARNING Failure to use wheel chocks might allow the vehicle to roll which could result in death or serious injury 2 Bleed all air from the air suspension system 3 Suitably supp...

Page 2: ...ntering ring faces toward the cover plate The centering ring Fig 3 of the receiver tube is used to center the receiver tube on the trailing arm receptacle When the removal tool is used the centering ring must always face toward the trailing arm receptacle Fig 3 Receiver tube with centering ring Centering Ring REMOVAL Fig 1 Identification of removal tool components Preparing the Pivot Bush Replacem...

Page 3: ...ing will reduce vehicle stability which could result in death or serious injury 3 Lubricate the Drive nut 6 and the threads on the threaded rod 4 Use standard grease 4 Insert the threaded rod end 4 of the correctly pre assembled removal tool through the hole in the pivot bushing until the centering ring of the receiver tube 5 fits the bushing receptacle Screw the drive nut 6 onto the threaded rod ...

Page 4: ...he bushing position locator of the replacement bushing must be aligned with the line on the outside of the receiver tube The orientation index marked Top must face upward as illustrated in Fig 10 If need be readjust the pivot bushing 5 Push the pivot bushing and the drive disc 6 completely into the receiver tube as shown in Fig 11 Fig 8 Lubricated receptacle Fig 9 Lubricated pivot bushing Fig 10 C...

Page 5: ... opposite axle side as described earlier and install a replacement pivot bushing as outlined 8 Operate the Hydraulic pump until the drive nut 6 and the pivot bushing are completely drawn into the receptacle 5 and the receiver tube becomes loose and can be removed Fig 13 Fig 14 Checking spring center Fig 15 Checking installation position FINAL STEPS Upon replacement of the pivot bushing perform the...

Page 6: ...onths Service Intervals for Steel Hanger Brackets First check after 5000kms Further checks every 12 months Pivot bolt Inspection torque 1 200 Nm Shock absorber bolt Inspection torque 600 Nm Tightening torques for SAF air suspension systems M12 SW19 40 Nm M16 SW24 180 Nm for steel plunger piston 80 Nm for plastic plunger piston M30 SW46 400Nm 120o Tightening torques SAF INTRA with aluminum hanger b...