Engineering manual - SAB 193-233-283 S A-frame (including ATEX)
162/175
008831 en 2022.02
15. Commissioning instructions
This chapter describes:
•
The dangers that may occur when commissioning instructions and safety precautions
are not observed.
•
How to start up this equipment in a safe way.
•
How to prepare a safe and effective start-up.
This chapter is primarily intended for inspectors and supervisors.
15.1
Safety precautions
Danger!
Risk of injury to personnel and damage to equipment! In addition to the safety precautions in
this document, always read the safety precautions belonging to this equipment before start.
Failure to comply with safety precautions may cause death or injury to personnel. It may also
cause damage to or destruction of the equipment.
15.2
Preparations for commissioning
Final check of installation
Before the plant is put into operation, the installation must be checked one last time, see sub-
section
7.33 Final installation check.
Personnel requirements
The personnel who is going to start up the plant must be competent and have a thorough
knowledge of refrigeration technique. It is moreover necessary that the personnel knows the
refrigeration plant and its construction and mode of operation. The instructions in this manual
must be read before start-up.
Johnson Controls Denmark offers courses which deal with operation of and service on the unit
in question. It is recommended that both the supervisor and the operator take these courses.
Training
It must be made sure that all personnel have been trained so that the requirements listed under
Personnel requirements
above are complied with.