I N S TA L L AT I O N I N S T R U C T I O N S
B YO S 2 S L I D E
FIG. 10
FIG. 11
FIG. 12
FIG. 13
STEP 3: ENTRY SECTION ANCHOR ASSEMBLY - Continued
The 20˚ support must have a minimum concrete embedment depth of 24” from bottom of anchor as shown in
Fig. 10. Anchor may be mounted in ground or with minimum 18” diameter tube.
When oriented correctly, the bottom of the entry frame support will be level as shown in Fig. 11.
The vertical portions of the support frame should be plumb (level in both axis). See Fig. 12 & 13 below.
NOTE:
When slide is assembled and leveled as per instructions, the bolts on the entry support frame and anchors
may be tightened.
TIP: Once all the flume sections are assembled and the flange bolts are correctly tightened, do a water test with
a garden hose to ensure there are no flume to flume leaks.