Heavy bundles and crates should be spread out on the roof to avoid overloading the roof structure. Place
the material directly over major supports such as beams or trusses.
!
Bundles of tubing should be positioned parallel to the slope of the roof so they don’t roll down slope
when unbundled.
!
Use caution when cutting metal bundle straps as the tension on the strap may cause it to spring up
potentially causing injury.
M
ATERIAL
S
TORAGE
If the material is going to be stored outdoors for any period of time, we recommend covering it with plastic or
tarps. Bundles of tubing and hat section can be left uncovered if the load is raised at one end to allow water to run
off.
T
OOLS
The following is a list of recommended tools to perform the installation:
1.
200’ tape measure
2.
String line
3.
6” “Torpedo” level
4.
Construction crayon
5.
Ear plugs
6.
Safety glasses
7.
Heavy duty extension cords
8.
Large Vice Grip Clamps
9.
Open end and socket wrench set
10.
Power drill
11.
½” drive power impact driver
12.
Cordless drill/driver gun
13.
Self-leveling laser level with tripod
14.
Power skill saw with metal cutting blade
15.
Reciprocating saw with metal cutting blade
I
NSTALLATION
R
EVIEW
F
RAME
P
ARAMETERS
In the following sections of this installation guide we will cover steps involved in assembling frames and attaching
panels. To prepare, please review the assembled view of the frame in Figure 1. This drawing illustrates how the
frames are intended to be built. Height and Span are determined by choices made in the
RoofScreen Frame Kit
Selection Guide
found in our Online Store. Other dimensions shown in Figure 1 should be followed as closely as
possible to comply with maximum frame spacing listed in Table 1 of the
Frame Kit Selection Guide
. If for any reason