5
E10037-180424
PROBEX
2 OPERATING INSTRUCTIONS
2.1
ASSEMBLING THE EQUIPMENT
Referring to the figure below, assemble all parts of the PROBEX system.
Note 1 :
Two short optional hydraulic lines
can be used instead of the long regular tubing for
speeding up saturation and calibration processes.
Note 2 :
The ball and the notch on the tubing quick connects must be
aligned for connection. Then, turn the ring to misalign the ball
and the notch in order to prevent accidental disconnection
when inflating the PROBEX. This will prevent the PROBEX
from getting accidentally stuck in a borehole.
Note 3 :
WARNING: When disconnecting Lemo connectors, hold
the connector itself and pull outward. Never pull on the
cable
Note 4 :
WARNING: The operator must ensure that all 4 hydraulic connections to the pump
and to the PROBEX probe are properly made to avoid potential damage to the
hydraulic system.