![RITE-HITE Dok-Lok STR-4100 Installation Manual Download Page 8](http://html1.mh-extra.com/html/rite-hite/dok-lok-str-4100/dok-lok-str-4100_installation-manual_1464528008.webp)
8
Pub. No. 1243 — April 2008
RITE-HITE
®
STR-4100 DOK-LOK
®
Installation Manual
HYDRAULIC INSTALLATION
1.
Drill two holes through the dock wall for hydraulic
hoses to pass through. Make sure holes are free of
debris or sharp edges prior to passing hoses
through wall. Conduit may be required in some
applications to protect hoses.
2.
Route hoses from DOK-LOK, through dock wall and
connect to power unit. Make sure hoses are capped
to keep out debris. See figures 5, 6 & 7.
NOTE:
For optional power unit mouting location.
See page 16.
3.
Secure hoses to dock face to prevent possible
damage. Any extra hosing should be coiled and
secured to the inside dock wall below the power
unit.
4.
Fill power unit reservoir using the supplied hydraulic
fluid.
5
Complete electrical installation per schematics.
NOTE:
Schematic’s are located inside control box.
INSTALLATION CONT.
Hydraulic Power Unit
Pass Hoses Through Wall
Using Conduit As Required
Wire Power Unit
Into Control Box
Outside Electrical
Junction Box
Three Sensor Wires
Hydraulic Hoses Secured
To Dock Face
Pit Center Line
Dock Floor
Approach
Control Box
FIGURE 5 - HYDRAULIC INSTALLATION