Foundation box assembly.

Assemble the CA.275 foundation box referring to Fig. 4.
Fasten the individual parts, using the self-tapping screws 4.8x9.5 
supplied.
Alternatively, 

 4x10 mm rivets can be used, which are also supplied.

Open the 

∅ 

50 mm hole for the passage of the corrugated cable duct. 

Only open the highlighted hole (F) which refers to the direction of 
impact of the casing.
Also open the most appropriate drainage holes (H1/H2).
Then fasten the frame K to the casing using 4 lag bolts and 8 nuts . 

Laying the foundation box

Proceed with the insertion of the foundation box (Fig. 6) inside the 
excavation, checking that:
- the positioning dimension is correct
- the crate is perfectly horizontal (use a level)
- the expected direction of impact is correct.
Prepare the passage of the 50mm 

 corrugated sheath for the 

passage of the connection cable to the control unit.
Even if the drainage test gives a positive outcome, you are however 
advised to prepare a ∅ 90mm drainage tube to drain the casing on 
the foundation gravel.
Add another 125mm gravel until the drainage tubes are covered.
The concrete must be appropriately compacted (regarding the level 
of the cast, consider the possible thickness of the floor).
The concrete must be properly compacted, taking into account the 
possible thickness of the pavement in the casting level.
Wait a few days for the concrete to set before installing the bollard 
in the foundation box, protecting the box with a waterproof sheet 
in the meantime.

Electrical connections.

With reference to figure 6, prepare the electrical connections using 
a 16x1.5mm2

 

multipolar cable for all models.

Only use cables that are suitable for the type of use required by 
the installation and that comply with current local regulations.

Block the cable with two ties. 
Inside shunt box B, there is terminal board (Fig.7) for connection 
of the ramp to the MAX.CP control unit.
For further information, refer to the instructions supplied with the 
MAX.CP control unit.

Installation of the bollard.

As shown in figure 8, to allow the bollard to be inserted inside its 
foundation box, it is necessary to provide at least 1.5m of extra 
connecting cable (ref. C) from the base of the bollard to the begin-
ning of the foundation box.
Use the two G eyebolts supplied to lift the bollard and install it inside 
the foundation box, paying attention to the cable as it descends.
Figure 9 shows the insertion position of the bollard in the foundation 
box in relation to the intended direction of impact.
Secure the bollard to the foundation box using the 10 M12x25 
stainless steel screws, as shown in Figure 10.

Installation of two bollards

In the case of particularly large gates, it is possible to install two or 
more bollards as shown in figure 11.
The MAX.CP control unit is able to pilot two SPARTACUS bollards.

Emergency manual release

If necessary, the bollard can be lowered manually to allow vehicles 
to pass.
As indicated in Figure 12, unscrew the Allen screw highlighted with 
a 10mm key, remove the screw and exert pressure downwards, 
the ramp will start to lower.
The unlocking system does not require resetting.

Installation manual

GB

Summary of Contents for SPARTACUS 275/600

Page 1: ... di installazione Installation manual I GB Dissuasore idraulico automatico Automatic hydraulic bollard Made in Italy RLXXXXXXX Rev 00 GB Parking and passage semi automatic rising bollard E Disuasor de tránsito de aparcamiento y de paso ...

Page 2: ......

Page 3: ...SPARTACUS 3 6 7 4 1 2 3 5 8 5 1 2 600 mm 275 600 800mm 275 800 825mm 275 600 1025mm 275 800 5 4 7 m m CA 275 600 CA 275 800 C 5 4 7 m m 527 mm Ø 50 mm 2 8 7 m m 2 7 5 m m S Ø 90 mm ...

Page 4: ...4 SPARTACUS 3 Ghiaino Gravel Ø 8 20 mm 1300mm 275 800 1100mm 275 600 1025mm 275 800 825mm 275 600 1000 mm 1000 mm 275mm ...

Page 5: ...SPARTACUS 5 4 4 8x9 5 4x10mm oppure or 16x 4 8x9 5 4x10mm oppure or 8x F H1 H2 F K IMPACT DIRECTION REMOVE ATTENZIONE Aprire solo il foro che si trova sul lato opposto alla direzione d impatto ...

Page 6: ...TACUS 400mm Ghiaino Gravel Ø 8 20 mm Cemento Concrete Tubo Pipe PVC Ø90 Tubo Pipe PVC Ø90 Guaina Corrugata Ø50 Flexible sheath Ø50 Guaina Corrugata Ø50 Flexible sheath Ø50 IMPACT DIRECTION IMPACT DIRECTION 5 ...

Page 7: ...SPARTACUS 7 C B 6 7 1 2 3 4 5 6 7 8 9 10 11 M 1 E V SWC SWO COM COMBL 8 1100mm 275 600 1500mm 275 800 G C ...

Page 8: ...8 SPARTACUS 10 9 IMPACT DIRECTION 10x 10x M12x25 ...

Page 9: ...SPARTACUS 9 11 400mm x 400mm CP MAX IMPACT DIRECTION 12 ...

Page 10: ...garanzia del prodotto e RISE Srl declina ogni responsabilità ai fini della sicurezza e del buon funzionamento dell impianto L installatore deve fornire all utilizzatore tutte le informazioni necessarie per l uso e la manutenzione dell impianto e per la manovra manuale e d emergenza Deve consegnare e l utilizzatore deve richiedere il libretto con le avvertenze e le norme d uso e manutenzione Il tra...

Page 11: ... Figura 3 realizzare uno scavo di 1000x1000 mm della profondità di 1300 mm versione 275 800 3 1100mm versione 275 600 Predisporre un fondo di ghiaia di 275 mm si consiglia della ghiaia di granulometria 8 20 per un buon drenaggio Assicuratevi che la ghiaia si ben compattata Prestare attenzione alle quote e al livellamento del sottofondo DATI TECNICI MODELLI 275 600 275 800 275 600 I 275 800 I 275 6...

Page 12: ...pattato per quanto riguarda il livello del getto considerare l eventuale spessore della pavimentazione Attendere qualche giorno per il periodo di maturazione del calcestruzzo prima di installare il dissuasore nella cassa di fondazione proteggendo nel frattempo la cassa con un telo impermeabile Collegamenti elettrici Con riferimento alla figura 6 predisporre i collegamenti elettrici utiliz zando un...

Page 13: ...s that are part of the RISE system Any modification alterations or tampering with the RISE system or the use of non original RISE accessories will cause the product warranty to lapse and RISE Srl declines any responsibility with regards to safety and proper system operation The installer must provide the user with all information necessary for system use and maintenance along with manual and emerg...

Page 14: ...tion Drainage test Before inserting the foundation box in the excavation carry out the test described below which is INDISPENSABLE for assess ing the level of permeability of the soil and taking the most suitable measures to ensure that water does not stagnate in the excava tion but is absorbed as quickly as possible Pour 40 litres of water into the excavation and wait 30 minutes If the water take...

Page 15: ...in the meantime Electrical connections With reference to figure 6 prepare the electrical connections using a 16x1 5mm 2 multipolar cable for all models Only use cables that are suitable for the type of use required by the installation and that comply with current local regulations Block the cable with two ties Inside shunt box B there is terminal board Fig 7 for connection of the ramp to the MAX C...

Page 16: ... oder die Verwendung von nicht originalem RISE Zubehör führen zum Erlöschen der Produktgarantie und RISE Srl lehnt jede Verantwortung für die Sicherheit und das ordnungsgemäße Funktionieren des Systems ab Der Installateur muss dem Benutzer alle notwendigen Informationen für den Gebrauch und die Wartung des Systems sowie für den manuellen und Notfallbetrieb zur Verfügung stellen Die Broschüre mit d...

Page 17: ...wässerungstest Vorbereitung der Ausgrabung Nehmen Sie unter Bezugnahme auf Abbildung 3 einen Aushub von 1800 x 1500 mm mit einer Tiefe von 1700 mm version 275 800 und 1100mm version 275 600 vor Bereiten Sie ein Kiesbett von 275 mm vor für eine gute Entwässerung wird Kies 8 20 empfohlen Stellen Sie sicher dass der Kies gut verdichtet ist Achten Sie auf die Abmessungen und Nivellierung des Unterbode...

Page 18: ...chend verdichtet werden bezüglich der Betonierhöhe ggf die Dicke des Bodenbelags berücksichtigen Der Beton muss unter Berücksichtigung der Dicke des Bodenbelags in der Höhe des Betons entsprechend verdichtet werden Warten Sie einige Tage bis der Beton ausgereift ist bevor Sie den Poller in den Fundamentkasten einbauen und den Kasten mit einer wasserdichten Folie schützen Elektrische Anschlüsse Ber...

Page 19: ... annulera la garantie du produit et RISE Srl décline toute responsabilité pour la sécurité et le bon fonctionnement du système L installateur doit fournir à l utilisateur toutes les informations nécessaires à l utilisation et à la maintenance du système ainsi qu aux opérations manuelles et d urgence Il doit livrer et l utilisateur doit demander le livret avec les avertissements et les règles d uti...

Page 20: ... la Figure 3 faire une excavation de 1000x1000 mm avec une profondeur de 1300 mm version 275 800 ou 1100mm version 275 600 Préparez un lit de gravier de 275 mm un gravier de granulométrie 8 20 est recommandé pour un bon drainage Assurez vous que le gravier est bien compacté Faites attention aux dimensions et au nivellement du sous plancher DONNÉES TECHNIQUES MODÈLES 276 600 276 800 276 600 I 276 8...

Page 21: ...épaisseur du revêtement de sol au niveau de la coulée Attendez quelques jours que le béton mûrisse avant d installer la borne escamotable dans le caisson de fondation tout en protégeant le caisson avec une bâche étanche Connections électriques En référence à la figure 6 préparer les raccordements électriques à l aide d un câble multipolaire 16x1 5mm pour tous les modèles N utiliser que des câbles ...

Page 22: ...ule la garantía del producto y RISE Srl declina cualquier responsabilidad inherente a la seguridad y el buen funcionamiento de la instalación El instalador debe dar al usuario toda la información necesaria para el uso y el mantenimiento de la instalación y para la maniobra manual y de emergencia Debe entregar y el usuario debe solicitar el manual con las advertencias y las normas de uso y mantenim...

Page 23: ...ar una excavación de 1000x1000 mm con una profundidad de 1300mm versión 275 800 o 1100mm versión 275 600 Preparar un fondo de vaina de 275 mm se aconseja una vaina con una granulometría 8 20 para un buen drenaje Asegurarse de que la vaina esté bien compactada Prestar atención a las alturas y a la nivelación del fondo Instrucciones de montaje ES DATOS TÉCNICOS MODELOS 275 600 275 800 275 600 I 275 ...

Page 24: ...a al nivel del chorro considerar el eventual espesor del suelo El hormigón debe estar adecuadamente compactado conside rando en el nivel del chorro el eventual espesor del suelo Esperar algún día para el periodo de maduración del hormigón antes de instalar el disuasor en la caja de cimentación protegiendo entretanto la caja con una lona impermeable Conexiones eléctricas Remitiéndose a la figura 6 ...

Page 25: ...dall originale disponibile presso il produttore Benincà Luigi Responsabile legale Velo d Astico 16 02 2021 EU Declaration of Conformity DOC Manufacturer s name Rise S r l Postal Address Via della Tecnica 10 36010 Velo d Astico VI Italia Telephone number 39 0444 751401 E mail address info riseweb it Declare that the DOC is issued under our sole responsibility and belongs to the following product Mo...

Page 26: ...dall originale disponibile presso il produttore Benincà Luigi Responsabile legale Velo d Astico 16 02 2021 EU Declaration of Conformity DOC Manufacturer s name Rise S r l Postal Address Via della Tecnica 10 36010 Velo d Astico VI Italia Telephone number 39 0444 751401 E mail address info riseweb it Declare that the DOC is issued under our sole responsibility and belongs to the following product Mo...

Page 27: ... risulta conforme alle disposizioni imposte dale seguenti direttive Direttiva 2014 30 EU Direttiva 2011 65 EU Direttiva 2014 35 EU Sono state applicate le norme armonizzate e le specifiche tecniche descritte di seguito EN 61000 6 2 2005 EN 61000 6 3 2007 A1 2011 EN 60335 1 2012 A11 2014 EN 60335 2 103 2015 Il Certificato di Conformità di questo documento corrisponde all ultima revisione disponibil...

Page 28: ...RISE S r l Via Capitello 45 36066 Sandrigo VI Italy Tel 39 0444 751401 www riseweb it info riseweb it ...

Reviews: