17
GENERAL
➧
Check that the pellet container is full and
the combustion chamber is clean and con-
tamination free.
FIRST COMMISSIONING/
PROGRAMME SETTINGS
After filling the supply container and con-
necting the stove to the mains electrical
supply, press the ON/OFF key on the inter-
nal operating unit and SB (Standby) is
displayed.
“SB” = standby operation
Now program your control for your indivi-
dual requirements as follows:
(See page 29 for menu navigation).
Two heating intervals can be programmed
for each weekday. No heating times are
programmed in the factory. Press “MENU”
on the operating unit and the display shows
the following:
“MO” = Monday
Now press “ENTER” and the display shows:
“S1” = start first heating time,
6 the number is the time in hours
(0 to 23 hours) e.g. see window 6 Hour.
By pressing the “+” or “-” keys the
heating time can be changed in hourly
steps as required. The desired value is con-
firmed with “ENTER” and is then saved.
The display shows
“E1” = end of first heating time,
By pressing the “+” or “-” keys the heating
time can be changed in hourly steps as
required. The desired value is confirmed
with “ENTER” and is then saved. The
display shows
“S2” = start of second heating
time,
After entering the second heating time
and confirming with “ENTER” the display
shows
“E2” = end of second heating
time,
After entering the switch off point of the
second heating time and confirming with
“ENTER” the new valued is saved and the
display now shows:
CAUTION: During the ignition process the grate
door must be closed.
The electronic ignition does not work if the grate
door is open.
When the pellet container of the stove is filled
for the first time, no pellets are conveyed to the
fire tray for about 10 minutes. You can put a
handful of pellets in the fire pan to avoid a new
start process.
SB
MO
S1
6
E1
8
S2
16
E2
20
MO
8 . D E V I C E C O M M I S S I O N I N G / C O N T R O L
P R O G R A M M I N G / C O N T R O L O P T I O N S
EN
GL
ISH
Summary of Contents for PREMIO
Page 1: ...M A N U A L P R E M I O 8 k w The life and soul of your home R I K A S T O V E S ...
Page 2: ...2 View from rear Intake air duct combustion air Fig 1 Fig 2 Flue pipe connection ...
Page 3: ...3 Fig 3 ...
Page 4: ...4 Fig 4 ...
Page 5: ...5 Fig 5 ...
Page 6: ...6 Fig 6 ...
Page 31: ...E N G L I S H ...
Page 32: ...1 3 E C D E C L A R AT I O N O F C O N F O R M I T Y E N G L I S H 32 ...
Page 33: ...E N G L I S H 33 ...
Page 36: ...W A R R A N T Y Customer Address Stamp Z Nr 2212 0200 00 Art Nr Z32248 Prod Nr 01 2008 ...