resideo Aquastat L4006 Series Installation Instructions Manual Download Page 2

L4006,L4007 AQUASTAT CONTROLLERS

95-6120B—05

2

Installing the Immersion Well 

On existing installations, shut off the power and remove 

the old control. If the old immersion well appears 

suitable, and if the adapter clamp on the Aquastat 

controller fits the old well spud, this well need not be 

replaced. 

To install new well: 

1.

If the system is filled, drain system to a point below 

the boiler tapping.

2.

Remove old well from boiler tapping. 

3.

Install the immersion well. Both 1/2 and 3/4 inch x 

14 NPT wells are available. Depending on size of 

boiler tapping and model ordered, a reducer fitting 

may be required. 

4.

Fill the system. Make sure that the well is screwed 

in tightly enough to prevent leakage. Do NOT use 

the case as a handle to tighten well after controller 

is secured to well. 

Fig. 1. Internal view showing L4006 (model with 

horizontal well).

For Installation of Sensing Bulb in 
Immersion Well 

1.

Loosen screw (at top of case, above scale setting), 

and remove cover. Loosen 2 screws that secure 

adapter clamp. See Fig. 1.

2.

Insert the sensing element into the immersion well. 

3.

Fasten the case of the Aquastat controller to the 

well with the adapter clamp. Make certain that the 

clamp is properly positioned over the groove of the 

well spud. Also be sure the flange at the opening of 

the well fits snugly into the opening of the case. 

The sensing bulb must bottom in the well for best 

temperature response. 

Fig. 2. Mounting bracket placement for vertical or 

horizontal mounting.

M38421

SETPOINT

INDICATING DIAL

DIFFERENTIAL

ADJUSTMENT

WHEEL

ADAPTER CLAMP

SCREWS

IMMERSION

WELL

MODELS WITH FIXED DIFFERENBTIALS DO NOT INCLUDE

ADJUSTING WHEEL.

VERTICALLY MOUNTED IMMERSION WELL IS ATTACHED

TO THE BOTTOM OF THE CASE.

L4006G INCLUDES TWO SPST SWITCHES.

1

2

1

2

SPST

SWITCH

3

3

M38422

VERTICAL MOUNTING

HORIZONTAL MOUNTING

Summary of Contents for Aquastat L4006 Series

Page 1: ...rained experienced service technician 4 After installation is complete check out product operation as provided in these instructions CAUTION Disconnect power supply before beginning installation to prevent electrical shock or equipment damage Mounting The boiler manufacturer generally provides a tapping for insertion of the Aqua stat controller s sensing element This tapping is located in a repres...

Page 2: ...howing L4006 model with horizontal well For Installation of Sensing Bulb in Immersion Well 1 Loosen screw at top of case above scale setting and remove cover Loosen 2 screws that secure adapter clamp See Fig 1 2 Insert the sensing element into the immersion well 3 Fasten the case of the Aquastat controller to the well with the adapter clamp Make certain that the clamp is properly positioned over t...

Page 3: ...Hookup for oil fired summer winter hydronic system with domestic hot water using L4006A or B L4007 A or B This Is typical where control for domestic hot water is added or where each Aquastat controller is mounted in a separate location Fig 6 Typical hookup for gas fired system with domestic hot water using L4006A E or L4007A M8774C SENSING BULB BULB COMPRESSION FITTING SEALING WASHER ADAPTER CLAMP...

Page 4: ...urer s recommendations To adjust insert a screwdriver in the slotted screw type head located beneath the window in the cover Turn the scale to the desired control point Manual Reset If the device includes manual reset model L4006E be sure to press the red reset button on the front of the case to make sure that the controller is not locked out on safety In checking out the system adjust the limit s...

Page 5: ...d immersion pour montage horizontal INSTALLATION Avant d installer ce Produit 1 Lire attentivement les instructions Le fait de ne pas les suivre risque d endommager le produit ou de constituer un danger 2 Vérifier les caractéristiques spécifiées dans les instructions et indiquées sur le produit et s assurer que celui ci correspond bien à l application à laquelle il est destiné 3 L installateur doi...

Page 6: ... proposées Selon l ouverture du raccord de chaudière l utilisation d un réducteur peut s avérer nécessaire 4 Remplir le système S assurer que la gaine est bien vissée afin d éviter les fuites NE PAS utiliser le boitier comme poignée pour serrer la gaine après que le régulateur ait été fixé à la gaine Fig 1 Vue interne du L4006 modèle avec gaine montée horizontalement Installation de l élément sens...

Page 7: ...lumage au mazout avec eau chaude domestlque utilisant un L4006A ou B L4007A ou B Ce genre de raccordement est courant lorsqu on ajoute un régulateur d eau chaude domestique ou lorsque chaque régulateur Aquastat est monté à un endroit différent Fig 6 Raccordement type d un système à allumage au gaz avec eau chaude domestique utilisant un L4006A E ou un L4007 A MF8774B BULBE RACCORD DE SERRAGE DU BU...

Page 8: ... chaudière À l aide d un tournevis à lame droite toumer la vis située sous la fenétre du couvercle jusqu au point de contrôle voulu Réarmement manuel Si l appareil offre une fonction de réarmement manuel modèle L4006E s assurer d appuyer sur le bouton de réarmement rouge sur le devant du boîtier afin que le régulaleur ne soit pas mis sous sécurité Pendant la vérification du système régler la limit...