Installation
Vacuum spray degassing — 28.08.2019 - Rev. B
English — 13
6.1
Incoming inspection
Prior to shipping, this device was carefully inspected and packed. Damages during transport cannot be excluded.
Proceed as follows:
1.
Upon receipt of the goods, check the shipment for
•
completeness and
•
possible transport damage.
2.
Document any damage.
3.
Contact the forwarding agent to register your complaint.
6.2
Preparatory work
Condition of the delivered device:
•
Check all screw connections of the device for tight seating. Tighten the screws as necessary.
Preparing the connection of the device to the facility system:
•
Barrier-free access to the facility system.
•
Frost-free, well-ventilated room.
–
Room temperature > 0 - 35 °C.
•
Drain for drain water.
•
Filling connection.
–
DN 15 according to DIN EN 1717.
•
Electric connection.
–
230 V~, 50 Hz, 10 A with upstream RCD (tripping current: 0.03 A).
Note!
Shut-off valves must be used at the connection point to the pipe network.
Note!
We recommend connection to the existing pipe network using a flexible hose connection (especially in buildings with
high noise abatement requirements).
6.3
Execution
CAUTION
Risk of injury due to tipping over of the device
Risk of bruising or crushing caused by tipping over of the device.
•
Ensure sufficient stability of the device.
•
Weigh down the bearing surface of the device's transport unit with suitable means.
Note!
The screw connections at the device may loosen when the device is moved to another location.
•
Before using the device check the screw connections for proper seating and sealing
Note!
Avoid leaks at the connections.
•
When connecting the device to the plant system, ensure that the connections for degassing and make-up are
not twisted.