CLEARANCES
TABLE 1
INDOOR INSTALLATION
MINIMUM CLEARANCES FROM COMBUSTIBLE SURFACES
Models
Heater Side
122-322
Floor
See Note 1
Rear
1"
Water Side
12”
Other Side
1"
Top
1"
Vent
2"
Note 1
. Do not install on carpeting.
When installed according to the listed minimum clearances from combustible construction materials, the
Raypak heaters can still be serviced without removing permanent structural construction around the heater.
However, for ease of servicing, we recommend a clearance of at least 24” in front, and at least 18” on the
water connection side. This will enable the heater to be serviced in its installed location, that is, without
movement or removal of the heater.
Clearances less than minimum, may require removal of the heater to service either the heat exchanger or the
burner tray. In either case, the heater must be installed in a manner that will enable the heater to be serviced
without removing any structure around the heater.
9
TOP VIEW
FRONT VIEW
Summary of Contents for 122-322
Page 6: ...HI DELTA COMPONENT LOCATION 6 BACK LEFT SIDE FRONT See detail page 7 See detail page 7 ...
Page 7: ...7 General Information GasValve Detail Air Shutter Adjustment ...
Page 17: ...17 SINGLE HEATER DOMESTIC HOTWATER WITH ONE STORAGE TANK ...
Page 35: ...DIRECT VENT Vertical Venting Category I VERTICALVENTINGTABLE 35 SECTION J 4 ...
Page 41: ...41 WIRE DIAGRAM MODELS 122 322 Reference Drawing Number M152564C ...
Page 50: ...Fig 241093 50 ...
Page 51: ...51 HEATEXCHANGERDETAIL ...
Page 52: ...52 ...
Page 53: ...53 ...
Page 54: ......