27
INITIAL SYSTEM SET-UP
1)
Fill tank with water only. (If positive displacement pump is used, open pressure
relief valve, PRV).
2)
Place MASTER ON/OFF switch to ON and BOOM ON/OFF switches to OFF.
3)
Place RATE 1/RATE 2/MAN switch to MAN.
4)
Place POWER ON/OFF switch to ON.
5)
Verify that Boom Widths, SPEED CAL, METER CAL, VALVE CAL, and RATE CALS have been
entered correctly into the Console. In SELF TEST mode, enter the normal sprayer
operating speed.
6)
Run pump at normal operating RPM.
7)
If centrifugal pump is used, proceed with Step 8. If positive displacement pump
is used, set pressure relief valve (PRV) to 65 PSI [450 kPa].
8)
Verify that boom valves operate and that no nozzles are plugged by operating the
BOOM ON/OFF switches.
9)
Place all BOOM ON/OFF switches to ON.
10)
Hold the MAN ADJ switch in INC position until pressure is at its maximum. This
assures that the motorized Control Valve is fully open. Verify maximum pressure
and RATE. (Pressure gauge is not supplied).
NOTE: A pressure gauge MUST be installed to properly monitor the system.
11)
Adjust agitator line hand valve for desired agitation. Verify maximum pressure
is still present.
12)
Hold the MAN ADJ switch to DEC position until pressure is at its minimum. This
assures that the motorized Control Valve is fully closed. Verify minimum pressure
and RATE. If minimum pressure and RATE can not be obtained, consider by-pass
plumbing system in Appendix 3.
Summary of Contents for SCS 460
Page 1: ...SCS 460 Installation Service Manual P N 016 0159 479 Rev K 09 15 Copyright 2009 2015 ...
Page 3: ......
Page 4: ... ...
Page 50: ... ...