FIGURE 5. Hardware Assembly
UPPER TANK BASE FRAME INSTALLATION
1. Mount the upper tank base frame onto the top cross tube.
NOTE:
The tank base frame is heavy. This is a two person lift.
FIGURE 6. Installed Base Tank Frame
2. Secure the upper base frame to the sprayer skid with the 7/16” hardware. There will be two slots on each side of
the base that will align with the slots in the skid.
3. Secure the upper base frame to the support tubes using 1/2” hardware. Do not tighten the hardware at this
time.
LOWER FRAME SUPPORT INSTALLATION
1. Position the lower tank straps (P/N 107-0172-588) under the upper cross tube and secure to the upper tank
base frame.
Bolt
Washer
Washer
Lock Nut
Tank Base
Frame
1/2”
Hardware
7/16”
Hardware
Summary of Contents for ICD Sidekick Pro
Page 48: ...CHAPTER 5 44 ICD Sidekick Pro Injection for Case Trident Installation Manual ...
Page 57: ...P N 016 0171 675 Rev A 53 SYSTEM DIAGRAMS ...
Page 58: ...CHAPTER 6 54 ICD Sidekick Pro Injection for Case Trident Installation Manual ...
Page 60: ...INDEX 56 ICD Sidekick Pro Injection for Case Trident Installation Manual ...