CONCRETE PAD CONSTRUCTION
Dimensions given for the pad are based on soil bearing
shear of 2000 P.S.F. These figures may have to be adjusted
depending on local soil conditions.
1. Construct form for mounting pad according to
dimensions shown in Figure 1 and 2
2. Locate mounting pad according to dimensions given in
illustration.
3. Level top edge of form.
4. Set reinforcing bars and wire mesh.
5. Mix concrete, pour mixture into form. Level and finish
surface after pouring is complete.
6. Allow pad to cure for 48 hours, and remove forms.