3–Using DMS
Creating a Data Migration Job Group
3-6
ISR654606-00 A
A list of attributes with formatting and current values will follow.
Enter a new value or simply press the ENTER key to accept the current value.
If you wish to terminate this process before reaching the end of the list
press 'q' or 'Q' and the ENTER key to do so.
Index WWPN, PortId Symbolic Name Target Type
0 20:78:00:c0:ff:d5:9a:05, 00-00-00 HP MSA2012fc-0 Src+Dest
1 50:00:1f:e1:50:0a:e1:49, 82-07-00 HP HSV200-1 Src+Dest
2 50:06:01:60:4b:a0:35:de, 82-03-00 DGC RAID-2 Src+Dest
3 50:00:1f:e1:50:0a:37:18, 00-00-00 HP HSV210-3 Src+Dest
Please select a Target Id from the list above ('q' to quit):
0
Symbolic Name (Max = 128 characters) [HP MSA2012fc-0]
Target Type (1=SrcTarget, 2=DstTarget, 3=Src+Dest 4=None Target) [3 ]
Bandwidth for Migration (0=Array Bandwidth, 50-1600 MBps ) [0 ]
Enable Load Balancing (0=Enable, 1=Disable) [Enabled ]
Array based licensed applied.
All attribute values for that have been changed will now be saved.
Creating a Data Migration Job Group
The HP StorageWorks mpx Manager provides both GUI and CLI interfaces to
create data migration job groups.
Creating a Data Migration Job Group in the GUI
Follow these steps to create a data migration job group in the HP StorageWorks
mpx Manager.
To create a data migration job group in the GUI:
1.
In the left pane, click the
Services
tab to open the Services page.
By default, the MPX200 shows
Group 0
created under the
Data Migration
Jobs
item.
2.
Right-click
Data Migration Jobs
, and then on the shortcut menu, click
Add
Group
.
3.
In the Input dialog box, type a group name that you want to assign to
administer a set of data migration jobs, and then click
OK
.
4.
In the Security Check dialog box, type the data migration user password
(default is
migration
), and then click
OK
.