Installation Guide /SolarBase Low Ballast Flat Roof System

5

Installation Guide V 1.4 - NO.:PZ30-IM01-14

All drawings and dimensions in this installation guide are for a generic reference. The Clenergy PVezRack® SolarBase 
is to be optimized to suit specific conditions for each project and documented in a construction drawing. As a result, 
major components of the Clenergy PVezRack® SolarBase may be provided in section sizes and lengths that vary from 
those shown in this guide. The installation process detailed in this instruction guide remains the same regardless of 
the component size. In case you need to do any on-site modifications or alteration of the system in a way that would 
be different from the construction drawing please provide marked up drawings/sketches for Clenergy’s review prior 
modification for comment and approval.

- System Overview -

 

M8 Nuts: 18-20N·m

M8*35 bolts: 10-12N·m

M8 Nuts: 8-9N·m

M8*25 bolts: 18-20N·m

U bolts M8*58: 8-9N·m

M6*14 bolts: 8-9N·m

Precautions during Stainless Steel Fastener Installation

Improper operation may lead to deadlock of Bolts and Nut. Follow the steps below to reduce this risk

Reduce the friction coefficient

(1) Ensure that the thread surface is clean (no dirt or contaminant)
(2) Apply lubricant (grease or 40# engine oil) to fasteners prior tightening to avoid galling or seizing in the threads;

General installation instructions

(1) Apply force to fasteners in the direction of thread; 
(2) Apply force uniformly, to maintain required torque;  
(3) Professional tools and tool belts are recommended; 
(4) Avoid using electric tools for final tightening;
(5) Avoid working at high temperatures;

Safe Torques

Please refer to safe torques defined in this guide as shown in below; In case power tools are required, Clenergy 
recommends the use of low speed only. High speed and impact drivers increase the risk of bolt galling (deadlock) If 
deadlock occurs and you need to cut fasteners please make sure that there is no load on the fastener before you cut it. 
Avoid damaging the anodized or galvanized surfaces.

Installation Dimensions

Summary of Contents for SolarBase

Page 1: ...SolarBase Low Ballast Flat Roof System Installation Guide V 1 4 NO PZ30 IM01 14 Last Updated Mar 2022 ...

Page 2: ...s manual thoroughly prior to installing PVezRack SolarBase This manual provides supporting documentation for building permit applications relating to PVezRack SolarBase system The PVezRack SolarBase parts when installed in accordance with this guide will be structurally adequate During installation please comply with the appropriate occupational health and safety regulations Please also pay attent...

Page 3: ...pe Socket spanner Marking pen Components ER S SB S10 Support Leg for SolarBase ER BB SB 900 Ballast Bar for SolarBase EZ GC MC40 Module Clamp 40 mm ER WD SB10 17 A3 Wind Deflector for SolarBase EZ GL B Grounding Lug Tools and Components Note tools in the figure are only used for rack system not included in supply scope Consult system installation personnel about electronic part installation tools ...

Page 4: ...e Low Ballast Flat Roof System 3 Installation Guide V 1 4 NO PZ30 IM01 14 System Overview 1 Support Leg 2 Ballast Bar 3 Module Clamp 40 mm 4 Wind Deflector 5 Grounding Lug Overview of PV ezRack SolarBase System Overview 1 2 3 4 5 ...

Page 5: ...tallation Guide V 1 4 NO PZ30 IM01 14 System Overview Note Red circles highlight installation of Module Clamp 40 Take 1650x990x40 PV module as an example Installation angle is 10 and distance between front and rear parts of component is 532mm Installation planning ...

Page 6: ...m U bolts M8 58 8 9N m M6 14 bolts 8 9N m Precautions during Stainless Steel Fastener Installation Improper operation may lead to deadlock of Bolts and Nut Follow the steps below to reduce this risk Reduce the friction coefficient 1 Ensure that the thread surface is clean no dirt or contaminant 2 Apply lubricant grease or 40 engine oil to fasteners prior tightening to avoid galling or seizing in t...

Page 7: ... neck bolts as shown in Figure 1 Installation Instructions According to specification of ballast adjust distance between both square neck bolts Figure 1 Figure 2 Put rubber protection gasket into Support Leg and make sure the hole centre of rubber gasket is aligned with bolt centre as shown in Figure 2 Figure 3 According to installation specification use tools such as tape string and marker pen to...

Page 8: ...n tightly as shown in Figure 4 and 5 Recommended torque 8 9 N m for M8 Bolts Attention Wind Deflectors are installed on Support Legs of the last row Two adjacent Wind Deflectors will be overlapped as shown in Figure 6 Installation Instructions Figure 6 1 Nut 2 Washer 3 Plain washer 4 Fixing plate Figure 7 Figure 8 Use U bolt M8 58 to lock Wind Deflector tightly as shown in Figures 7 and 8 Recommen...

Page 9: ...ort Leg Pay attention to installation direction of PV module as shown in Figure 11 Fasten the frame of PV module and Support Leg with Module Clamp 40 as shown in Figure 12 Adjust Module Clamp 40 to ensure that it s located in the middle of preassembled parts of Support Leg and fasten tightly While fasten the Bolts M8 25 hold the Module Clamp 40 to ensure it unmovable as shown in Figure 13 and 14 R...

Page 10: ...nding Lug Fix the Grounding Lug on Ballast Bar of the longest row along vertical direction as shown in Figure 19 install one Grounding Lug per row and fasten tightly Fix the Grounding Lug on Ballast Bar of the longest row along vertical direction as shown in Figure 19 install one Grounding Lug per row and fasten tightly Fix the Grounding Lug on Ballast Bar of the longest row along vertical directi...