Installation Guide /SolarBase Low Ballast Flat Roof System
9
Installation Guide V 1.4 - NO.:PZ30-IM01-14
Adjust Module Frame Back Mounting Clip along
fore-aft direction; ensure the frame of PV module will
be held by Mounting Clip as shown in Figure 16 and 17.
Fasten Bolts M8*35 and Square Neck Bolts M8*45
tightly in order.
Recommended torque:
10-12N·m for Bolts M8*35
Recommended torque:
18-20N·m for Square Neck Bolts M8
Install Grounding Lug
Fix the Grounding Lug on Ballast Bar of the longest row
along vertical direction as shown in Figure 19, install one
Grounding Lug per row and fasten tightly.
Fix the Grounding Lug on Ballast Bar of the longest row
along vertical direction as shown in Figure 19, install one
Grounding Lug per row and fasten tightly.
Fix the Grounding Lug on Ballast Bar of the longest row
along vertical direction as shown in Figure 19, install one
Grounding Lug per row and fasten tightly.
- Installation Instructions -
Figure 16
Figure 17
Figure 18
Repeat above operations to install the rest PV modules
as shown in Figure18.
Figure 19
Figure 20