21-26
Installation instructions for AL320 Device
1
、
Open the packing for the well packed mainpulator complete(AL320
Device)carefully and place it onone side of the bead breaker blade on the
machine body;
2
、
Put one of the vertical arm padding plates(2 pieces/machine,see Picture3 )
onto the horizontal slot steel ,aim it at the hole on the slot steel;
3
、
Put the vertical arm complete onto the padding plate and aim it at the hole, the
thread the four bolts & flat washers(see Picture 1 & 2 ) through the holes;
4
、
Place the other vertical padding plate onto the bolt(below ) the slot steed ), install
the flat washers,spring washers & the nuts(see Picture 4,5,6) in turn, then fasten
them carefully;
5
、
Connect the Pu pipe with the joint of the device;
6
、
Refer the below drawings & the list on the left for the other installation operations
5. Operation Test
1). Connect to air source; make sure the pressure of air source is enough.
2). Pull up pneumatic-controlled valve, the upper part of the machine moves up.
3). Release pneumatic-controlled valve, the upper part of the machine stops.
4). Press pneumatic-controlled valve, the upper part of the machine moves down.
5). Move
6. Operation
Functions of the machine.
1). Auxiliary fixes of dismounting head and insert crowbar Dismantle the side of tire
according to correct rim size, press the upper side of tire with tire press roller ,fix the
dismounting head and insert crowbar(figure 6-1),move up the tire press roller and
Summary of Contents for TC-512A
Page 17: ...17 26 13 Electric Connection Diagram...
Page 20: ...20 26...
Page 25: ...25 26...
Page 26: ...26 26...