background image

 
Step 6:

 

Circuits being laid at 100mm or 200mm centres must be laid in a spiral 
configuration. The first loop of pipe should be laid around the perimeter 
of the area to be covered by that circuit. The next loop of this circuit 
should be laid either 200mm from the first loop of pipe for 100mm 
centres or 400mm from the first loop of pipe for 200mm centres.

 
 

 
 

 
 

Step 7:

Continue to loop the pipe into the centre of the panels leaving 
enough space to form a double return (‘S’ shape in the centre 
of the loop).

 

Step 8:

Now work back out from the centre by filling the space between the 
inwardly spiralling loop of the primary circuit ensuring the pipe is laid 
at the correct spacing centres.

 
 
 
 
 

 

 

 

 

 

 

 

 

 

18mm pipe installation formation

Where 300mm centre spacing is require (18mm pipe systems only) 
a meander pattern can be used. The pipe simply crosses the room 
from one side to the other encapsulating 3 castellations at each 
return bend.

 
 
 
 
 

 
 
 

Conduit pipe

A 400mm length of conduit pipe should be fitted over the under floor 
heating pipe in any situation where damage may be caused to the 
pipe i.e. where the pipe passes through internal walls or doorways, 
where the pipe emerges through the floor up to the manifold 
or where the pipe passes through either an expansion or day joint. 
Preformed long radius bends can also be used to provide a neater 
solution if required. 

A section of conduit pipe 400mm long should be fitted around the 
heating pipe where the pipe passes through the edge insulation strip, 
e.g. room to room, or through expansion joints within the floor.

Conduit pipe should also be used where the pipe leaves the floor 
adjacent to the manifold. This can be threaded down the pipe 
after the pipework has been installed.

14

15

Expansion joint 

BS EN 1264-4 recommends that an expansion joint is constructed 
in stone and ceramic finished screeds for every 40m

2

 of floor area 

at a maximum length of 8m and an aspect ratio of 2:1. 
An expansion joint is also required in long narrow areas such 
as corridors, etc.

The image below shows a typical arrangement where the pipes 
pass through either an expansion or a day joint. A strip of edge 
insulation is used to provide the expansion capacity.

 

For further information regarding floor screeding requirements 
for under floor heating systems please refer to BS8204-1 or the 
BISRIA Guide: Screeds with Under Floor Heating.

Testing 

Step 9:

Once the pipes circuits have been installed and pressure tested the 
screed cover can be applied. Care should be taken to ensure that 
the screed is tightly compacted around the pipe to ensure that no 
voids are present. The system should remain under pressure (6 bar) 
in order to prevent the risk of any damage being caused to the 
walls of the pipe whilst the screed is being applied.

Laying the screed 

Step 10:

The overall quality and thickness of a sand and cement screed 
should meet the requirements of BS8204-1 which stipulates that 
in domestic or light commercial applications a minimum thickness 
of 65mm should be used. The thickness of alternative coverings, 
such as anhydrite or polymer modified screeds, may differ depending 
on construction requirements. This information should therefore 
be provided by the specialist screed manufacturer/supplier.

After the screed has been laid the floor should be covered with 
a membrane to retard the drying out process, particularly in warm 
weather. The floor should be allowed to cure and dry naturally until 
full strength is reached in accordance with relevant British Standards 
and manufacturers’ instructions (approx 30 days for sand and 
cement and concrete floors). Under no circumstances should the 
under floor heating system be used to artificially dry/cure the screed 
as this could cause the screed to crack and seriously undermine 
the integrity of the floor construction. Once the screed has fully 
cured the under floor heating system can be switched on and the 
manifold flow temperature slowly increased up to the calculated 
design temperature.

Finishing

Timber floors 

Many people are concerned by the effect of heat on a timber 
floor, but this concern is misplaced. The important factor is the 
floor moisture content.

Timber floors can be laid directly over the screed at a moisture 
content of 10-11% which during the heating season will reduce 
to 8-9% and may cause a small amount shrinkage.

The floor will re-absorb some moisture when the heating is not 
operating and the moisture content will increase to 12-13%.

Application of timber floors over solid floor systems 

Where solid oak flooring is to be laid on a solid floor, joists can 
be fitted at 1m centres to provide a fixing point for the boards.

Insulation, solid floor panels and pipe can be laid between 
the joists and screed laid level with the top of the joists 
(see diagram below).

 
 

Individual circuits of pipe are then laid between each set of joists 
with care being taken to ensure the screed is completely dry prior 
to fitting the solid oak covering (see diagram).

90°

180°

Screed
Timber floor covering
Solid floor plate
Joist at 1m spacings

Pipe
Conduit 

Insulation
Sub floor

Summary of Contents for Under Floor Heating Systems

Page 1: ...s Broomhouse Lane Edlington Doncaster DN12 1ES Tel 01709 770 000 Fax 01709 770 001 2410 London Road Mount Vernon Glasgow G32 8XZ Tel 0141 778 8822 Fax 0141 778 2703 Dromore Road Lurgan Craigavon Co Ar...

Page 2: ...revious printed copies will become out of date The latest version of our installation advice including a downloadable version of the current Technical Installation Guide can be found at our trade webs...

Page 3: ...xtensive back up service Technical representation available to discuss systems in general and particular projects www ufch com Technical Installation CD Specialist Technical Hotline on 01709 770000 En...

Page 4: ...he floor screed is required by Building Regulations Edge insulation also acts as an expansion joint Floating Floor When installed in floating floors Polyplumb pipe is simply pressed in to the pre form...

Page 5: ...r requires a bespoke design You then simply input data for each room providing floor type room size and control zones to calculate the required pack All packs have a single order code and include all...

Page 6: ...h when heated will reduce to 8 9 and cause only a very small amount of shrinkage The floor will re absorb some moisture when the heating is not operating and the moisture content will increase to 12 1...

Page 7: ...d around the perimeter of the room using staples so as to prevent possible risk of the panels lifting Preparing the pipe Step 4 You will need to remove the coil from the bag leaving the shrink wrap on...

Page 8: ...ted the screed cover can be applied Care should be taken to ensure that the screed is tightly compacted around the pipe to ensure that no voids are present The system should remain under pressure 6 ba...

Page 9: ...nder pressure whilst the flooring is laid Finishing The room can then be finished by fitting 18mm or 22mm tongue and groove sheets of chipboard glued on the edge over the floating floor system Mark th...

Page 10: ...hed downwards and away from the underside of the timber finished floor covering as this could lead to potential underperformance of the system Testing Step 4 Once the pipe circuits have been installed...

Page 11: ...These can be fixed directly through the spreader plate down in to the joists below It is important to indicate the position of pipework in areas where the additional fixing of items such as carpet gri...

Page 12: ...heir high output at relatively low flow temperatures Modular Heating Panels are ideal for maximising heat efficiency and lowering energy consumption In most installations it is not necessary to cover...

Page 13: ...should be selected The span is defined as the free space from wall to wall that needs to remain uninterrupted by trimmers or other services Ideally install MHP panels prior to other services whenever...

Page 14: ...omes into direct contact with it Always ensure that electrical cables are not in physical contact with the MHP panels using tape or a polythene strip Finishing Once you have connected your system up t...

Page 15: ...for heavyweight floor coverings such as ceramics or where the floor covering needs to be secured directly to the panel e g solid wood Overlay Lite is a high compressive strength lightweight insulated...

Page 16: ...is should be the first consideration for most projects The more structural nature of Overlay however makes it ideal for direct tiling or application of floor finishes which need to be fixed or screwed...

Page 17: ...mple of blanking in a bathroom Example of squaring off an irregular room plan Room layouts The following diagrams show some examples of room shapes pipe requirements and interruptions pillars hearths...

Page 18: ...wood floors they can be discretely screwed through the tongue and groove directly into the Overlay panel avoiding pipe circuitry to minimise movement in the floor covering If over boarding with 6mm p...

Page 19: ...r covering as normal It is advisable to mark out pipe positioning to avoid stapling pipes when fitting carpets 36 37 Overlay Lite for lightweight floor coverings Installation Laying end returns Step 1...

Page 20: ...stic hot water primary circuits To provide independent hydraulic control of the entire system it is important that the installation is designed as an S Plan or S Plan Plus configuration which allows f...

Page 21: ...d in under floor heating systems is less than that required for radiators or stored hot water If these other services are connected to the same boiler it will be necessary to control the water tempera...

Page 22: ...iring centre and slave units Available in two surface finishes and offers the following features Large touch screen display with high visibility blue LED backlight On screen display shows current stat...

Page 23: ...distribution pipe work Connection from nearest radiator 260mm 200mm Pump Pipe thermostat Heating return Heating flow Under floor heating flow Under floor heating return Thermostatic blending valve Pu...

Page 24: ...ible tap connectors for the simplest method of connection Close all under floor heating circuits except one by screwing down the blue caps and closing the isolating valves situated on top of the manif...

Page 25: ...resistant to the build up of scale Short term chlorination for disinfection of supply pipe work and normal levels of chlorine in UK domestic water supplies will not have an adverse effect on the integ...

Page 26: ...ng should be done with all switches on and room thermostats calling Fault finding complete Adjust pump speed and set flow rates in accordance with the system design data as provided NO NO Is the boile...

Page 27: ...Manufacturing quality assurance In accordance with BS ES ISO 9001 2000 BSI registered firm Certificate FM00318 Installation standard To follow the recommendations of BS5955 Part 8 2001 Plastic Pipewo...

Page 28: ...OR HEATING REQUIREMENTS Manifold Position s Please also indicate on drawing Floor Type Solid Suspended Floating MHP Overlay Overlay Lite Ground Floor 1st Floor 2nd Floor CONSTRUCTION DETAILS If NOT to...

Reviews: