7
INSTALLATION INSTRUCTIONS
Concrete Pad
• Pour concrete pad a minimum size of 24” x 24” at
least 6” above ground
• Be certain that concrete base is placed below frost line.
Check local building codes.
• Operator frame can be fastened to the concrete pad
using four 4½” x 4” concrete expansion bolts.
• Necessary electrical conduit can be placed in the
concrete pad area prior to adding concrete. Align with
the hole in the bottom of the chassis.
• Nominal distance between the gate and chassis is 5”
(see fig. 6).
Post Mounting
• Drill three holes through 2” x 2” steel posts for
mounting 3/8” x 3” galvanized steel bolts with washer
and nut (posts, bolts, washers, and nuts all purchased
separately).
• When post mounting operator, be sure to cover the
bottom opening in gate frame which is normally used
for electrical conduit when pad mounting.
• Nominal distance between the gate and chassis is 5”
(see fig. 6).
Figure 3
INSTALLATION INSTRUCTIONS
SLIDERfig4
Figure 4
Steel posts
(not included)
SLIDERfig3
Concrete pad,
6” above ground
Access hole for electrical connection
Chassis
4½” x 4” concrete
expansion bolts
Access hole for
electrical connection
Chassis
3/8” x 3”
galvanized steel
bolts (not
included)
Summary of Contents for SL2000