Legion Solar Installation and Operations Manual
Install the Battery Commander to the Photovoltaic Panel
Install ‘Z’ Brackets for Do-it-Yourself Mounting
Note: Skip this section if you are installing the PV panels on a roof racking rail system.
Copyright © 2021 PLX Devices Inc.
11
Step1:
1 Battery Commander is used for every 2 photovoltaic
panels.
Install Battery Commander in Location A.
Fasten Battery Commander to the PV panel in the same
manner as the Micro Inverter.
Step2:
Install the Antenna. If Battery Commander is within 30ft of
Solar Regulator and is unobstructed by dense materials such
as metal, concrete, tile you may install the Antenna directly
on Battery Commander.
Otherwise, we recommend using the included SMA coax wire
(1) to locate your Antenna (2) out and above the PV panels
for improved wireless performance and reliability.
Use the included aluminum plate (3) designed to be installed
on the Legion Solar End Clamp or Mid Clamp with a 1/4-20
nut (4).
Step1:
8 ‘Z’ Brackets are used for every 2 photovoltaic panels.
Locate the 8 oval holes on the rear of the PV panel.