6.0

 

MAINTENANCE 

 
 

6.1

 

GENERAL 

 
 
Maintenance, inspection and operation activities have to be carried out in compliance with the regulations in force on the matter in the place 
of installation of the equipment (type and frequency). Before performing any kind of intervention, it is important to ensure that the slam-shut 
valve has been closed, that the inlet & outlet isolating valves have been closed and  that all of the pressure has been discharged from the 
piping between the slam-shut valve and those isolating valves. Maintenance interventions are strictly bound to the quality of the conveyed 
gas (impurities, humidity, gasoline, corrosive substances) and to the filtration efficiency. 
Therefore, it is always recommended to perform preventive maintenance interventions whose periodicity shall be determined according to 
the following aspects, unless specified by regulations already in force: 
 

 

The quality of the conveyed gas; 

 

The status of cleaning and preservation of the piping upstream of  the regulator: as a rule, for example, after the first start of the 
plants, more frequent maintenance interventions are required due to the uncertain internal cleanliness of the piping; 

 

The reliability level required by the reduction plant. 

 
Before starting disassembling the equipment make sure: 
 

 

To have  a series  of  original spare  parts  available. Spare  parts shall  be  original spare  parts  by Pietro Fiorentini  bearing  in mind 
that the most important parts such as membranes are marked. 

 

To have a set of tools as shown in table 6.4. 

 
For proper maintenance, the recommended spare parts are unequivocally identified by tags indicating: 
 

 

The SS layout drawing number of the equipment in which they can be used; 

 

The position given on the SS layout drawing of the equipment; it is suggested to replace all rubber parts; for this purpose, use the 
suitable spare part kit available on Pietro Fiorentini website. 

 

NB. The use of non-original parts relieves Pietro Fiorentini S.p.A. from any liability whatsoever. 

 
Pay attention to discharging vents & drains to a safe area during the depressurization activities. To avoid risks related to the formation of 
sparks due to particles of impurities inside the discharge lines, it is recommended to keep fluid speed lower than 5 m/sec. 
Moreover,  for  those  parts  that  can  be  positioned  or  oriented  in more  than  one  way  during  re-assembly,  it  is  suggested  to  add  reference 
marks on those parts before disassembling. 
Finally, it shall be underlined that the O-rings and the sliding mechanical parts (stems, etc.) have to be lubricated before reassembling them, 
by  applying  a  thin  layer  of  silicone  grease.  Before  commissioning,  it  is  necessary  to  verify  the  external  tightness  of  the  equipment  at  a 
suitable pressure for assuring the absence of external leaks.  
 
The internal tightness of the slam-shut devices, when they are used as safety accessories according to the PED Directive, must be checked 
at a suitable pressure able to assure the internal tightness at the maximum working pressure expected.  
These checks are essential in order to assure the safe use at the intended operating conditions; they shall, in any case, comply with  the 
national regulations in force. 

 
 
 

 

 

Summary of Contents for DILOCK 106

Page 1: ...EN TECHINICAL MANUAL Slam Shut Valves DILOCK507 512 106...

Page 2: ...2 MT 237 EN ed 2015 Rev A EN DILOCK Basic version INLET PRESSURE CONTROL PRESSURE DILOCK 507 512 106...

Page 3: ...etail natural gas plants must show features complying with the law provisions or regulations in force in the place of installation or at least complying with the standards EN 12186 or EN 12279 The ins...

Page 4: ...r pressure decrease according to the calibration pressure 1 2 OPERATION OF THE SLAM SHUT VALVE Figure 1 Slam Shut Device LA The slam shut valve fig 1 tripping in case of minimum and maximum pressure i...

Page 5: ...ranges of the different available springs FEATURES OF THE SPRINGS FOR LA BP SLAM SHUT VALVES Code Colour De Lo d Calibration range mbar Tripping due to maximum pressure 64470112RO RED 34 43 2 2 30 49...

Page 6: ...damages during transport the inlet piping has been cleaned in order to remove any residual impurities such as welding scraps sand paint residues water etc The arrangement normally forecast is the one...

Page 7: ...7 MT 237 EN ed 2015 Rev A Figure 3 Overall dimensions...

Page 8: ...out 5 10 tube branch connections shall always be welded on the upper part of the piping itself and the hole on the piping shall not show any burrs or projections towards the internal side To avoid bre...

Page 9: ...ibrations in a very short time without disconnecting the sensing pipe during the periodic checks The peculiarity of this lies in the fact that during normal operation the pressure switch head receives...

Page 10: ...y PS maximum allowable pressure that can be born under safety conditions by the device body structure Pumax maximum operation pressure at device inlet DNi type of inlet connection to the device DNu ty...

Page 11: ...ot to create malfunctions 4 3 EXTERNAL TIGHTNESS AND CALIBRATIONS CHECK A For the slam shut devices connected to the downstream piping through the push three way switch valve proceed as follows Figure...

Page 12: ...am shut device is in closed position Open the inlet on off valve V1 Very slowly open the slam shut valve by pulling the proper bushing Partially open the relief valve 6 on the outlet piping Using the...

Page 13: ...turator gasket 526 deteriorated Replacement Obturator seat eroded or scratched Replacement Wrong release pressure Wrong calibration of the min and or max spring Perform the calibration again by acting...

Page 14: ...To have a set of tools as shown in table 6 4 For proper maintenance the recommended spare parts are unequivocally identified by tags indicating The SS layout drawing number of the equipment in which t...

Page 15: ...hat the pressure upstream and downstream of the same is zero DISASSEMBLING AND RE ASSEMBLING 6 3 DISASSEMBLING 1 Make sure that the slam shut device is in closed position 2 Disconnect the fittings bet...

Page 16: ...16 MT 237 EN ed 2015 Rev A 6 Remove the body cover springs 7 Extract the membrane assembly from the body 8 Remove the plug unscrew the nut and ring nut 9 Extract the shaft assembly from the top...

Page 17: ...Unscrew the valve seat from the body paying utmost care not to damage the sealing edges To re assemble the slam shut valve follow the procedure described for disassembly in reverse order Before reasse...

Page 18: ...nlet of the valve and using a foamy solution check the following tightness of the valve internal and external surfaces tightness of the slam shut valve 2 Operating very slowly pull the bushing of the...

Page 19: ......

Page 20: ...Via Enrico Fermi 8 10 36057 Arcugnano VI Tel 39 0444 968511 Fax 39 0444 960468 www fiorentini com R code generated on http qrcode littleidiot be...