Installation
ACCUCONTROL
20
59245(e)
6. Installation
6.1
Safety notices to observe during installation
Basic safety rules must be followed in order to ensure that the end product can be continually op-
erated in a safe manner. These rules must be observed while using the end product and while in-
stalling the ACCUCONTROL in the end product.
6.1.1
Pause interval for the ACCU
NOTICE
The following pause times for the ACCU must be observed. The unit must not be in
operation for at least 1 hour:
•
before commissioning,
•
before removal and
•
before changing the battery.
6.1.2
Avoiding electrical faults
The PLUG-IN CHARGER PB 4.5 has a connecting cable. When sizing your end product, remem-
ber that the connecting cable must never be squashed (e.g. by moving over it) during operations.
6.1.3
Ensuring operational reliability during installation
The safety and reliability of the end product containing DewertOkin components can be ensured by
using the proper construction methods described below.