IntelliChlor Electronic Chlorine Generator COMSYS-10 Installation Guide

Mount Power Center Banks  To Wall 

(Continued)

4. Remove the cover retaining screw and remove the cover from

upper side left PRIMARY power center and the lower left
side SECONDARY  power center.

Connect AC Power Wires and ORP Sensor Wires

1. Mount a JUNCTION BOX on the left

side of the Power Center Banks.

2. Run a CONDUIT (with 208VAC -

260VAC wires) from the AC
BREAKER to the junction box. Note:
This AC power should be on its own
breaker for future servicing.

Note: For 110VAC operations, each

power center will need to be re-
configured. A 110VAC wiring
diagram is provided on the inside of
each the power center covers.

3. Run conduit from the junction box into

each of the power centers located on
the left side (PRIMARY and
SECONDARY). A (knock-out) conduit
opening is provided on the bottom of
each of power centers.

Mount power centers to wall using four

(4) screws

Remove cover screw

and cover

Remove cover screw and cover

Mount power centers to

wall using six (6) screws

CPC103

CPC103

CPC202

CPC202

Summary of Contents for 520974

Page 1: ...IMPORTANT SAFETY INSTRUCTIONS READ AND FOLLOW ALL INSTRUCTIONS SAVE THESE INSTRUCTIONS INTELLICHLOR SALT CHLORINATOR COMMERCIAL SYSTEM COMSYS 10 P N 520974 INSTALLATION GUIDE...

Page 2: ...hours Comsys 10 5 cell 1 primary and 4 secondary produces ten pounds of chlorine per day The ORP system not provided is a separate device that monitors the available chlorine in the water and when ne...

Page 3: ...E PROCEEDING IMPORTANT SAFETY PRECAUTIONS PLEASE READ THE FOLLOWING Read all the safety precautions in this manual before attempting any electrical wiring Be sure to read and follow all safety Instruc...

Page 4: ...REAKER to the junction box Note ThisAC power should be on its own breaker for future servicing Note For 110VAC operations each power center will need to be re configured A 110VAC wiring diagram is pro...

Page 5: ...abeled WIRED FOR 220V Do not applyAC power yet 5 Connect the two 2 twisted wires labeled ORP SENSOR to the ORP chlorine controller panel AcuTrol etc not included in kit Carefully place the connection...

Page 6: ...t the two wires from the CPC202 into terminal block in same order as the wires already connected Be sure to match the wire colors GREEN to GREEN and YELLOW to YELLOW 10 Replace the cover on the upper...

Page 7: ...and the buttons can be pressed if needed CAUTION Do not install upside down 4 Verify water flow direction See the FLOW arrow located on the IntelliChlor cell near the input coupling IMPORTANT MANIFOL...

Page 8: ...r on the receptacle turn it slowly until the plug pins are inserted into the receptacle then twist it to lock it in place 2 Plug the four SECONDARY cell power connectors into each of the power centers...

Page 9: ...de PRIMARY SECONDARY SECONDARY Terminal Screw Connector CPC203 CPC103 SECONDARY SECONDARY Power Centers The PRIMARY and SECONDARYpower centers have been pre wired with communication wires as shown bel...

Page 10: ...is flashing the cell has become dirty and requires acid cleaning Turn off the circuit breaker to the power centers disable water flow through the manifold either an external valve or turn off the filt...

Page 11: ...h salt is in the water to produce chlorine cell is OFF 1 Add salt to the water and bring up to 3600ppm Allow it to mix for 24 hours 2 The salt level will be checked every 8 hours by the cells and disp...

Page 12: ...ion in order to minimize the corrosion and deterioration that is inherent in and around salt water pools PENTAIR WATER POOL AND SPA INC 1620 HAWKINS AVE SANFORD NC 27330 919 566 8000 10951 WEST LOS AN...

Reviews: