4 Assembly and installation [specialist]
2018/06
99423x063MGK7-mub-en
–
V01
15
Fig. 5
Fig. 6
9.
Punch out the holes at the marked areas
in the insulation (see figure 5).
10.
Push the insulation on the wall bracket
or on the stair bolts.
11.
Now push the fittings on the wall bracket
until the clips snap in.
12.
Pull the insulating back shell forward
to the fittings such that they snap in.
13.
Connect the cable with the pump and
insert the cable in the cable channel.
14.
Connect the CoolBloC to the installation
by using the pipes. The installation to
the piping must be carried out without
any tension.
15.
Connect the pump.
16.
Carry out a pressure test and
check all thread connections.
17.
Mount the insulation in the following
order:
•
Insulating element above the return pipe
•
Upper insulating element
for the thermometers
•
Lower insulating element
18.
Push the insulating foam in the opening
of the mixing valve segment until it forms
a flat surface.
19.
Mount the anti-rotation devices
with the retaining plate (fig. 6).
20.
Mount the thermometers.