1. Connect the charge hose to the charging cylinder
•
•
•
•
Connect the charge hose which was disconnected from
the vacuum pump to the valve at the bottom of the
cylinder.
•
•
•
•
If you are using a gas cylinder also use a scale and
reverse the cylinder so that the system can be charged
with liquid.
2. Purge the air from the charge hose
•
•
•
•
Open the valve at the bottom of the cylinder and use a
screwdriver to press the check valve on the charge set
to purge the air. (Be careful of the liquid refrigerant.)
•
•
•
•
The procedure is the same if using a gas cylinder.
3. Open the valve (low side) on the charge set and charge the
system with liquid refrigerant.
•
•
•
•
If the system cannot be charged with the specified
amount of refrigerant, it can be charge with a little at a
time (approximately 150g each time) while operating the
air conditioner in the cooling cycle.
However, one time is not sufficient, wait approximately
1 minute and then repeat the procedure. (Pumping
down pin)
This is different from previous procedures.
Because you are charging with liquid refrigerant from the gas
side, absolutely do not attempt to charge with large amounts of
liquid refrigerant while operating the air conditioner.
4. Immediately disconnect the charge hose from the 3-way
valve´s service port.
•
•
•
•
Stopping part-way will allow the refrigerant to be
discharged.
•
•
•
•
If the system has been charged with liquid refrigerant
while operating the air conditioner, turn off the air
conditioner before disconnecting the hose.
5. Mount the valve stem nuts and the service port.
•
•
•
•
Use a torque wrench to tighten the service port cap to a
torque of 1.8kg. m (18N.m).
•
•
•
•
Be sure to check for gas leakage.
9.3.1. Gas charging
(After evacuation)
Procedure
46
CS-SA9CKP CU-SA9CKP5 / CS-SA12CKP CU-SA12CKP5
Summary of Contents for CS-SA9CKP
Page 9: ...3 Dimensions 9 CS SA9CKP CU SA9CKP5 CS SA12CKP CU SA12CKP5...
Page 10: ...10 CS SA9CKP CU SA9CKP5 CS SA12CKP CU SA12CKP5...
Page 11: ...4 Refrigeration Cycle Diagram 11 CS SA9CKP CU SA9CKP5 CS SA12CKP CU SA12CKP5...
Page 12: ...5 Block Diagram 12 CS SA9CKP CU SA9CKP5 CS SA12CKP CU SA12CKP5...
Page 13: ...6 Wiring Diagram 13 CS SA9CKP CU SA9CKP5 CS SA12CKP CU SA12CKP5...
Page 17: ...Time Graph for soft dry operation 17 CS SA9CKP CU SA9CKP5 CS SA12CKP CU SA12CKP5...
Page 26: ...26 CS SA9CKP CU SA9CKP5 CS SA12CKP CU SA12CKP5...
Page 55: ...13 Exploded View CS SA9CKP CS SA12CKP 55 CS SA9CKP CU SA9CKP5 CS SA12CKP CU SA12CKP5...
Page 57: ...15 Exploded View CU SA9CKP5 CU SA12CKP5 57 CS SA9CKP CU SA9CKP5 CS SA12CKP CU SA12CKP5...
Page 61: ...17 1 REMOTE CONTROL 61 CS SA9CKP CU SA9CKP5 CS SA12CKP CU SA12CKP5...