Machine Maintenance Procedures
3-13
ODD Module Installation
0
1.
Install ODD bezel (E) on ODD module.(
Figure 3-8
)
2.
Install ODD bracket (D) on ODD module and secure two (2) screws (C). (
Figure 3-8
)
3.
Insert ODD module (B) into ODD module bay. (
Figure 3-7
)
4.
Install and secure screw (A) to lower cover. (
Figure 3-7
)
5.
Install battery.
ID
Size
Quantity
Screw Type
A
M2.5*6.0
1
C
M2.0*3.0
2
Summary of Contents for EasyNote TK11BZ
Page 1: ...Packard Bell EasyNote TK11BZ TK13BZ SERVICEGUIDE ...
Page 4: ...iv ...
Page 10: ...x ...
Page 11: ...CHAPTER 1 Hardware Specifications ...
Page 14: ...1 4 ...
Page 53: ...CHAPTER 2 System Utilities ...
Page 80: ...2 28 System Utilities ...
Page 81: ...CHAPTER 3 Machine Maintenance Procedures ...
Page 84: ...3 4 ...
Page 118: ...3 38 Machine Maintenance Procedures ID Size Quantity Screw Type B ICW50 CPU Thermal Screw 4 ...
Page 135: ...CHAPTER 4 Troubleshooting ...
Page 162: ...4 28 Troubleshooting ...
Page 163: ...CHAPTER 5 Jumper and Connector Locations ...
Page 172: ...5 10 Jumper and Connector Locations ...
Page 173: ...CHAPTER 6 FRU Field Replaceable Unit List ...
Page 174: ...6 2 Exploded Diagrams 6 4 FRU List 6 6 Screw List 6 21 ...
Page 194: ...6 22 FRU Field Replaceable Unit List ...
Page 195: ...CHAPTER 7 Model Definition and Configuration ...
Page 196: ...7 2 Packard Bell EasyNote TK11BZ TK13BZ 7 3 ...
Page 200: ...7 6 Model Definition and Configuration ...
Page 201: ...CHAPTER 8 Test Compatible Components ...
Page 202: ...8 2 Microsoft Windows 7 Environment Test 8 4 ...
Page 213: ...CHAPTER 9 Online Support Information ...
Page 214: ...9 2 Introduction 9 3 ...
Page 216: ...9 4 Online Support Information ...