45.
Roof Gussets
are positioned on the Middle Rafters. Slide gusset up slightly below top of rafter,
use level to square gusset and attach to rafters with 4 - 2” screws. Pilot hole each Gusset end with 1/8”
drill bit. Complete remaining Gusset.
46.
Identify Roof Panels. There are 2 Outside and 1 Middle Roof Panel per side.
Starting with outside rear panel, lift up and place on rafters.
Shingles overhang battens
on outside panels.
Shingles and battens
flush on middle panel.
Roof facing
down with
roofing felt
showing.
Outside Roof Panel.
Toll Free 1-888-658-1658 www.outdoorlivingtoday.com [email protected]
Page 20
44.
Attach
Simpson Strong Ties (22 degree bend)
to Top Wall framing and plates and also to the
underside of the rafters. Use 4 - 1 1/4” screws to secure. There are 5 Ties per side. Have two helpers
push the side walls at the top from the outside of shed until inside to inside measurement between the
side plates is 91”.
91” across
1 Strong Tie on Doubled Up Rafters
below top
of Rafter