Assembly
900-0123-01-00 Rev
A
21
Installing DC Shunts
Figure 16
DC Shunts
A single 500 Adc/50 mV shunt is
included with the GSLC. Up to two
more shunts can be installed as
needed. These shunts are used in
conjunction with the FLEXnet DC
battery monitor. See page 29 for more
instructions on wiring.
To mount DC Shunts:
1.
Place new shunts to the left of the
existing one. They will not be exactly
parallel to the first shunt, but will be
mounted to the lower left of it.
2.
Four mounting holes are located to the
lower left of the first shunt. Center
each shunt across one pair of
mounting holes. These should line up
with the mounting holes built into
each shunt.
3.
Using the screws included with the
shunt, attach each shunt to the
GSLC enclosure.
4.
Tighten until secure, but do not
over-tighten.
NOTE:
The GS-SBUS can be
purchased and installed to
connect the three shunts
together. See Figure 25 on
page 30.