Recommended sequence of operations 

 

 

General instructions

cgmcosmos

 system: Medium voltage switchgear  

and control gear, fully insulated in SF

6

 gas up  

to 24 kV with external cable test device

5.2.4.  Switch closing operation from the open position

1. 

Move the red handle to the left (this releases the access 

to the actuation shaft so the switch- disconnector can 

be closed).

2.  Closing operation:

a.  Manual operation

 (driving mechanism B) Insert 

the lever in the switch access (red area), move the 

actuating arM to one end and turn 90° CLOCKWISE.

Figure 5.6. 

Process of turning the lever

Figure 5.7. 

Switch-disconnector connected

b.  Motorised operation

 (BM driving mechanism) 

Activate the corresponding operation order.

If, for any reason, the motor stops halfway through a 

motorised operation, before restarting it you must 

finish the operation manually, so that the whole 

mechanism: sensors, controllers, etc., are in a reliable, 

effective and logical position for the control system of 

the motorisation when they connect with it again.

3. 

Verify that the cubicle is in connected position.

Summary of Contents for cgmcosmos-2lP

Page 1: ...IB cgmcosmos system Medium voltage switchgear and control gear fully insulated in SF6 gas up to 24 kV with external cable test device Synergrid AA10 General instructions IG 297 EN version 01 06 02 202...

Page 2: ...ectrical installations Personnel must be fully familiar with the instructions and warnings contained in this manual and in other recommendations of a more general nature which are applicable to the si...

Page 3: ...the switchgear and control gear assembly 22 4 8 Cable connections 22 4 8 1 Horizontal front connection 25 5 Recommended sequence of operations 27 5 1 Checking the gas pressure 27 5 2 Feeder function 2...

Page 4: ...functional switchgear and control gear Function cgmcosmos l Feeder K cgmcosmos p Fuse protection T Table 1 1 Single functional switchgear and control gear Multi functional switchgear and control gear...

Page 5: ...ngs spigots for side connection 2 Driving mechanism area 2 1 Name plate 2 2 Operating sequence plate 2 3 Actuation shafts see mimic plan for each model 2 4 LRM VDS system according to NBN EN 61243 5 3...

Page 6: ...1 3 2 Driving mechanism compartment This is the compartment in which the switch disconnector or the circuit breaker is actuated depending on the type of function The mimic diagram for the main medium...

Page 7: ...able test compartment Cable compartment This is located in the lower front section of the cubicle thus allowing front access to the medium voltage cables As standard it is designed to contain up to 2s...

Page 8: ...frequency withstand voltage kV fr Equipment rated frequency Hz Ir Equipment rated current A Manual of instructions Manual of General Instructions IG corresponding to the system Class Driving mechanis...

Page 9: ...m voltage switchgear and control gear fully insulated in SF6 gas up to 24 kV with external cable test device General description In addition another plate into the operation area of each mechanism is...

Page 10: ...e 1 min 28 32 50 60 Lightning impulse rated withstand voltage 75 85 125 145 Internal arc classification in accordance with IEC 62271 200 IAC AF AFL 20 kA 1 s IP rating gas tank IP X8 IP X8 IP rating e...

Page 11: ...red over a 24 hour period 35 C Maximum average relative humidity measured over a 24 hour period 95 Maximum average vapour pressure measured over a 24 hour period 22 mbar Maximum average vapour pressur...

Page 12: ...d control gear must be perfectly seated and fixed so that it cannot move about and possibly damage the equipment 2 1 Lifting methods The switchgear and control gear must always be kept upright directl...

Page 13: ...ing supports on the sides of the top of the cubicle The angle of pull should be as vertical as possible with an angle greater than 60 from the horizontal Figure 2 3 Lifting cgmcosmos cubicles with cha...

Page 14: ...to 40 C are also available 3 The switchgear must be protected from direct sunlight 4 The altitude will be no higher than 1000 m 5 The ambient air must not be significantly polluted by dust smoke corr...

Page 15: ...e 3 Detach the white polystyrene corner pieces 4 Unscrew the fixings between the base and the pallet 5 Remove the pallet handling the cubicle as indicated in section 2 1 6 Unpack the accessory box loc...

Page 16: ...lug kit Cubicle end assembly Nylon thread Plastic plugs Side cover Floor fastening assembly 4 3 Minimum installation distances The minimum distances to the walls and ceiling to be maintained in the in...

Page 17: ...the cables these dimensions may vary Feeder function Figure 4 4 Dimensions mm of cable trench for cgmcosmos l Trench needed for the feeder function L or T terminal 400 630 A Cable data Guiding radius...

Page 18: ...ht terminal D1 D2 Side cable input or output with straight terminal D3 D4 Figure 4 5 Dimensions of cable trench for cgmcosmos v Trench necessary for the fuse protection function Cable data Approximate...

Page 19: ...t difficult to connect it to the rest of the cubicles in the assembly The cubicles can be fastened to the floor in two ways 4 5 1 Floor fastening on a profile If the floor of the installation is not s...

Page 20: ...install the medium voltage cubicle assembly directly anchored to the floor The sequence for anchoring the cubicles to the floor is as follows 1 All the cubicle s functions must be in the earthing posi...

Page 21: ...dle on the cover to pull it up and forward 4 Anchor the first cubicle to the floor of the installation using screws at the points prepared on the base This will prevent vibrations or movements due to...

Page 22: ...h adapter for 13 mm Connect the end earthing bar marked with the symbol to the Installation s general earth connection Earthing the equipment is an essential condition for safety 4 8 Cable connections...

Page 23: ...ed PMA 1 250 25 25 95 PMA 1 250 25 25 95 PMR 1 250 25 25 95 PMR 1 250 25 25 95 RAYCHEM Shielded RSES 16 120 RSES 16 120 RSSS 16 95 RSSS 16 95 400 3M Not shielded 93 EE 8XX 2 25 95 93 EE 8XX 2 25 95 EU...

Page 24: ...22 35 185 PFISTERER Shielded CAT 20 630 95 240 RAYCHEM Not shielded UHGK RICS 120 300 UHGK RICS 95 240 IXSU RICS 16 800 IXSU RICS 16 800 1250 EUROMOLD Shielded 440TB 185 630 K440TB 185 630 Impregnated...

Page 25: ...e test device Installation 4 8 1 Horizontal front connection Tools 13 ratchet and spanner Single phase cable example with feeder function 1 Connect the earthing switch 2 Access cable compartment a Rem...

Page 26: ...4 kV with external cable test device c Connect the terminals d Secure the cables using the cable clamps Connect the terminal earth connectors if applicable and the cable screen earth connectors Figure...

Page 27: ...the manometer 5 1 Checking the gas pressure Each tank has a pressure gas with temperature compensation for checking the gas pressure which can easily be seen from outside the cubicle The pressure gau...

Page 28: ...ow b LRM VDS system according to NBN EN 61243 5 c Operation area RED for switch disconnector YELLOW GREEN for earthing switch d Status indicators BLACK for switch disconnector BLACK for earthing switc...

Page 29: ...tions 5 2 3 Isolating operation from the earthing position 1 Move the green handle to the right this releases access to the actuating shaft so the earthing switch can be opened 2 Insert the lever in t...

Page 30: ...ng mechanism B Insert the lever in the switch access red area move the actuating arM to one end and turn 90 CLOCKWISE Figure 5 6 Process of turning the lever Figure 5 7 Switch disconnector connected b...

Page 31: ...eration from the connected position 1 Move the red handle to the left as before this releases the lever access so the switch disconnector can be opened 2 Opening operation a Manual operation driving m...

Page 32: ...evice 5 2 6 Earthing operation from the isolating position 1 Move the green handle to the right this releases the lever access so the earthing switch can be closed 2 Insert the lever in the earthing s...

Page 33: ...test 1 Follow the steps from section 5 3 4 Earthing operation from the disconnected position 2 Open the access cover of the cable test compartment pulling up and out as shown in the figure Figure 5 12...

Page 34: ...n pistons Figure 5 14 Detail of the connection pistons 5 Connect the cable test device These driving mechanisms allow the opening of the earthingswitchafterremovingthecablecompartment cover preventing...

Page 35: ...is retained by means of a latch device It can then be released during the opening operation by manually driving this latch device The operation speed and strength are independent of the action of the...

Page 36: ...evice 5 3 2 Actuating levers Earthing switch actuating lever Figure 5 17 Type 1 lever detail anti reflex Switch disconnector actuating lever Figure 5 18 Type 2 lever detail anti reflex 5 3 3 Opening o...

Page 37: ...ition Start with the switch 5 and the earthing switch 6 in open positions Operate the lever in the direction indicated in Figure 5 20 Starting conditions circuit breaker open earthing switch open Figu...

Page 38: ...ontrol gear fully insulated in SF6 gas up to 24 kV with external cable test device 5 3 6 Earthing operation from isolating position Start with the switch 3 and the earthing switch 4 in open positions...

Page 39: ...emove the cable compartment cover It is essential to close the earthing switch Proceed as indicated in the following steps 1 Since this is a switch fuse combination cubicle any of thethreefusesblowing...

Page 40: ...ted in SF6 gas up to 24 kV with external cable test device 4 Open the bottom cover to access the cable compartment Figure 5 25 Cable compartment cover opening 5 Turn the handle on the fuse holder cove...

Page 41: ...eplace the blown fuse Avoid resting the carriage on any surface that could get dirt on the rubber seal or the contact Make sure that the end with the striker of the new fuse faces forward carriage ins...

Page 42: ...Lower the handle of the fuse holder by pushing it until the safety trigger engages Figure 5 31 Close the fuse holder 11 To close the cover first ensure that the clip is properly engaged and that the...

Page 43: ...63 80 100 15 24 10 24 6 3 6 3 10 16 16 16 20 20 25 31 5 40 50 63 80 80 20 24 10 24 6 3 6 3 6 3 10 16 16 16 20 20 25 31 5 40 50 50 63 80 125 Table 5 1 Recommended fuse calibres 1 Fuses recommended SIBA...

Page 44: ...sconnector and the earthing switch cannot both be closed at the same time 2 The cubicles have an interlock that prevents access to compartments for testing cables and medium voltage cables while the e...

Page 45: ...as earthing switches both in the open and closed positions Examples of locking with interlocks on feeder functions optional Example 1 Earthing switch interlocked in open position This avoids setting...

Page 46: ...tion indicated on the mimic diagram of the cubicle until it reaches the stop piece Figure 6 3 Detail of the interlocking sequence It is now that the position indicator is locked until the sequence to...

Page 47: ...and therefore unaffected by the external environment Class E2 electrical endurance tests mean that the breaking components are maintenance free The operating mechanism for the cgmcosmos system switch...

Page 48: ...cubicle by specialised personnel Please contact Ormazabal Driving mechanism l p B X O BM O O Group of auxiliary contacts 2 NO 2 NC switch X O Group of auxiliary contacts 1 NO 1 NC Earth connection X O...

Page 49: ...uoride SF6 9 SF6 isincludedintheKyotoProtocollistofgreenhousegases SF6 has a GWP Global Warming Potential of 22200 units TAR IPCC 2001 At the end of the product s life the SF6 contained in it must be...

Page 50: ...Notes General instructions cgmcosmos system Medium voltage switchgear and control gear fully insulated in SF6 gas up to 24 kV with external cable test device Notes IG 297 EN version 01 06 02 2020 50...

Page 51: ......

Page 52: ...Subject to change without prior notice For further infotmation contact Ormazabal www ormazabal com Ormazabal y C a IGORRE Spain...

Reviews: