7.2.
SEAL REPLACEMENT: HORIZONTAL AND BOTTOM SEAL
Each log includes two horizontal seals which are used to seal between logs. Additionally, some logs include a
separate bottom seal (only for the first log, please refer to the GAD).
Horizontal seal replacement
o
Step 1: Remove the log from the frame (See
Figure 15
, part#2).
o
Step 2: Remove the damaged seals and replace it by the new ones (See
Figure 16
, part#1). Add general
purspose Loctite to secure the seal in position.
Bottom seal replacement
o
Step 3: Remove the first log from the frame.
o
Step 4: Remove and replace the bottom seal (see
Figure 18
, part#3). Some logs include bolted bottom
seals (See
Figure 17
, part#4) by means of a stainless steel retainer (See
Figure 17
, part#5)
Figure 15
Figure 16
Figure 17
Figure 18