Oracle Talari T5200 | Hardware Guide
Installing the Talari Appliance
Rack Installation
Prior to installing the system in a rack, adhere to the following rack installation guidelines:
Ensure that there is adequate airflow through the rack, because restricted airflow
can lead to equipment damage.
Leave at least 1U of vertical space between the systems you install in a rack.
Ensure that the rack width and depth allows for proper serviceability and
cable management.
Ensure that the rack is properly secured to the floor or ceiling and is grounded.
Load the rack from the bottom up.
Load the heaviest component in the rack first.
Ensure that the rack is level and stable before removing components.
Do not move racks by yourself. At least two people are required to safely move
racks and stage equipment.
Ensure that cables are easily identifiable
.
Installing the Rack Mount Brackets and Rails
The T5200 ships with a rack mounting kit included. This appliance requires a four-post rack
for safe installation. Additionally, the outer rails extend from 27 inches to 36.4 inches. Follow
the steps below to install the rack-mount brackets.
Separate the Inner and Outer Rails
Separate the inner rail from the outer rail by pressing the locking tab on the inner rail.
Please see
Figure 7
.
1. Locate the rail assembly in the chassis packaging.
1 1