2x Front Outer Rails
2x Non-Threaded Brackets for 2-Post Racks (For use with your own cage
nuts and rack screws)
Assembly
1. Attach 1 selected mounting bracket to the raised oblong middle section of one of
the Front Outer Rails with a short rounded screw (contained in rack mounting
hardware bag). Ensure that the Front arrow on the bracket points towards the
front of the rail.
a.
Note:
The word “Limit” on the Front Outer Rail should still be visible once
the bracket is joined to the Front Outer Rail.
Oracle Talari E1000 | Hardware Guide
2-Post Rack Mounting
Layout & Required Components:
2x Front Outer Rails
2x Pre-Threaded (10-32) Brackets for 2-Post Racks
OR
2. Repeat with second Front Outer Rail.
Installation
9. Facing front of rack, install each assembled Front Outer Rail (with joined bracket)
to the two post rack using rack screws (not provided).
10. Slide the E1000 onto the rail arms until you hear the click from the Side Rail
Locks on the E1000 indicating proper installation.
Figure 6: Side View of E1000 Showing Side Rail Locks
1 7