![Oracle Sun Datacenter InfiniBand Switch 648 Installation Manual Download Page 89](http://html1.mh-extra.com/html/oracle/sun-datacenter-infiniband-switch-648/sun-datacenter-infiniband-switch-648_installation-manual_1646261089.webp)
Installing the Switch
79
4. Route each power cord to its respective facility power receptacle.
Use cable ties or hook and loop fastener straps to bundle and secure the cord.
5. Plug each power cord into the receptacle.
6. Energize the circuit breakers so that the power receptacles are live.
7. Verify that the status LEDs for each power supply indicate normal operation.
The OK LED should be lit and the Attention LED should be unlit. See
Power Supply Status LEDs” on page 80
Note –
At this time, power is being supplied to the CMCs. The CMCs are effectively
on and booting up. You might see the boot sequence on the management console.
Related Information
■
“Power Cord Requirements” on page 8
■
“Electrical Specifications” on page 3
■
“Attach the Management Cables” on page 76
■