Installing the Switch
109
▼
Attach Cables to the CXP Connectors
Note –
This procedure describes cabling the switch in a center split, left-right
symmetrical configuration.
1. Identify the prerequisite and subsequent tasks you must perform in
conjunction with this procedure, to install the switch.
See the table in
“Installation Sequence” on page 20
2. Bring the cables to the switch.
3. Install a cable shelf into the slot below the lowest line card.
a. Lift the cable shelf into a horizontal orientation, with the long rolled edge
towards you.
b. Locate where you want to install the cable shelf.
c. Move the cable shelf between and just above the branches of the cable tree
for the slot where you want to install the shelf.
d. Continue to move the shelf in, then lower the shelf into the tabs of the
branches.