![Oracle EXADATA X5-2 Installation And Configuration Manual Download Page 314](http://html1.mh-extra.com/html/oracle/exadata-x5-2/exadata-x5-2_installation-and-configuration-manual_1646081314.webp)
Data Center
Room Checklist
Items
Yes
No
N/A
Comment
Will the new
hardware
location require
any non-standard
cable lengths?
Is the floor to
ceiling height a
minimum of 2914
mm (114.72
inches)?
Is the depth of
the raised floor a
minimum of 46
cm (18 inches)?
Related Topics:
•
(page 1-28)
•
•
Stabilize Oracle Exadata Rack with Leveling Feet
(page 4-7)
A.3 Data Center Environment Checklist
Use this checklist to ensure that the data center environment requirements have been
addressed.
Data Center
Environment
Considerations
Yes
No
N/A
Comment
Does the
computer room
air conditioning
meet
temperature and
humidity
requirements?
Does the
installation floor
layout satisfy the
ventilation
requirements?