O P T E K
D P L - 2 4
12
OPERATION
1. Insure circuit breaker is in the “ON” position.
2. Activate “MAIN POWER” switch.
3. Activate “VACUUM PUMP” switch.
4. Chamber drawer may now be opened for inspection.
WARNING: PLATEN MUST BE IN POSITION WHEN CYCLING
MACHINE!
5. Return drawer to home position.
6. Activate “TOP” and “BOTTOM” Heaters by depressing and
illuminating switches beneath digital controllers.
7. Press "asterisk" and
"up" or "down" arrows
until desired
temperature is indicated
on digital readout.
8. Release "asterisk" and
note temperature
indication on readout.
9. A flashing green light below the temperature readout indicates the controller is
triggering the solid state relay to supply current to the respective heater blanket.
10. Allow 20-40 minutes for unit to reach set-point and stabilize, if (under 200
degrees F).
11. Product may now be processed through laminator.