Conducting a measurement
35
•
B
… In our example each Voltage Electrode has to be placed in a distance of 1 m to the left and
right of the control unit. This corresponds to the cable marker “1”. So you will put the electrode
at voltage cable marker “1” into the ground.
For all coming steps you will simply follow the instructions on this screen. After each measuring process
the device will show you how to replace the electrodes in the field before measuring the next scan point.
The following instruction scenarios might occur during your measurement:
•
You have to move the Power Electrodes (red socket)
outwards to the next cable marker. This will increase the
depth of the current scan point.
•
You have to move the Power Electrodes (red socket)
inwards to the previous cable marker. This will decrease
the depth of the current scan point.
•
You have to move the Voltage Electrodes (black socket)
outwards to another cable marker (several cable
markers might be skipped). This will be necessary if the
measured voltage is too low.
•
You have to move the Voltage Electrodes (black socket)
inwards to another cable marker (several cable markers
might be skipped). This will be necessary if the
measured voltage is too high.
OKM GmbH
Summary of Contents for FS Future GeoSeeker Mini
Page 1: ...FS Future Series GeoSeeker Mini User s Manual ...
Page 6: ......
Page 7: ...1 Introduction CHAPTER 1 Introduction ...
Page 12: ......
Page 13: ...2 Technical specifications CHAPTER 2 Technical specifications ...
Page 15: ...3 Scope of delivery CHAPTER 3 Scope of delivery ...
Page 30: ......
Page 48: ......