NewMar SPS 12-20 Installation & Operation Manual Download Page 7

P.O. Box 1306

 Newport Beach

   California 92663

   

  

Phone: 714-751-0488  

     Fax: 714-957-1621

     E-Mail: [email protected]

If the LVD functionality is not required, the load must still be connected to the Load connection (not directly onto 

the battery).

It is recommended that two wires are run in parallel for both the +v and –v Battery and Load connections. 14 

AWG wire should be used for the connectors. In situations where voltage drop is a concern, then a short length of 

14 AWG wire should be used from the SPS, connecting to a longer length of large cross section wire. 

Connectors supplied for the SPS are 4W Lumberg screw connectors. Each terminal on the connector is rated at 20 

Amps at 50° C.

To connect cable to Lumberg connector, strip back cable insulation approximately 1/4”, insert into connector and 

tighten screw.

2.4 

Temperature Compensation

Temperature Compensation Probes are available in different lengths. The end of the Temperature Compensation 

Probe should be attached to a terminal on a battery (the lug is isolated, so it doesn’t matter which terminal). Any 

excess cable should be neatly coiled. As the current in the Temperature Compensation Probe is minimal, it does 

not matter if the cable is longer than necessary (unlike the current carrying load and battery cables).

Warning

Do not reverse poloarity of the cables from the battery. This will blow an internal protection fuse, requiring the 
SPS to be returned for servicing.

Do not connect the Temperature Compensation Probe to the Site Power System until commissioning see 

Section 2.7 

- Start-Up

.

2.5 

Multiple Units

The SPS may be operated in parallel to provide greater current capability and to provide redundancy.

When SPS connected in parallel (and load sharing), alarm outputs on the rectifiers give the status of all the units. 

This means that you only need to connect one alarm card to the alarm circuitry when the rectifiers are connected 

in parallel.

The load and battery cables should be wired in parallel to the rectifiers as per the diagram in section 2.3. Each SPS 

should be fitted with a Temperature Compensation Probe connected to the same terminal on the same battery.

For load and alarm sharing, an alarm and control interface cable 

should

 be connected to each parallel SPS to 

ensure that all units load share automatically. When two or more units are connected in parallel, then you can 

use a simple RJ45 double adaptor to daisy chain the connection cable (max 6 rectifiers).

Any fuses or circuit breakers on the output of the rectifier must be placed after the SPS outputs have been 

connected together.

2.6 

Internal Alarm Card 

Two six position, green screw style connectors are provided for making alarm card wiring connections. The alarm 

card provides voltage free relay contacts in the event of:

• AC failure

• Rectifier failure

• Rectifier In Shut-Down Mode (over temperature, over voltage, current limit)

• High voltage output

• Low voltage output

7

Summary of Contents for SPS 12-20

Page 1: ...2 Troubleshooting 10 1 9 Input Over Voltage Shut Down 4 3 3 Fuses 10 1 10 Input Inrush Current Limiter 4 4 Adjustments 10 1 11 Over Temperature Shutdown 4 4 1 Standard Settings 11 1 12 Reverse Polari...

Page 2: ...e the present state of the rectifier and diagnose faults AC On This LED glows green to indicate that AC power is connected to the unit and that the primary stages of the rectifier are operating Shutdo...

Page 3: ...ches the battery ve supply the v is common with the battery Do not connect the Battery and Load v together The LVD voltage and the LVD Hysterisis voltage are preset in the factory but may be adjusted...

Page 4: ...if they fail 1 13 Parallel Rectifier Operation The SPS may be connected in parallel to source more current or to provide a degree of redundancy The rectifiers should have the load share signal connect...

Page 5: ...ethal even after the input supply has been removed The rectifier contains components at High Temperatures that may burn if touched 2 2 Positioning of SPS A great deal of care should be taken with posi...

Page 6: ...t outlet be used so the rectifier will not be accidentally unplugged from the supply When hard wiring AC input the IEC AC cord provided should be wired as follows BLK WHT GRN 120 VAC L N Safety Ground...

Page 7: ...w an internal protection fuse requiring the SPS to be returned for servicing Do not connect the Temperature Compensation Probe to the Site Power System until commissioning see Section 2 7 Start Up 2 5...

Page 8: ...fier Fail alarm Rectifier Off Normal and the Low Volts alarms will also activate Note that the AC Fail Relay has its own Common connector but all the other alarm outputs share a Common contact 2 6 2 R...

Page 9: ...y connections and then plug them into the SPS Re connect the mains and the Float Boost LED should glow first yellow then after about 10 seconds either green or yellow depending on the charge of the ba...

Page 10: ...e current drawn by the battery from the SPS is as expected Check that the battery takes the charge Connect the DC load to the SPS with AC off and disconnect the battery Turn AC on and check that the c...

Page 11: ...m back of unit with AC input socket on left 4 2 Adjust Float Voltage Connect a variable load set to minimum load to the battery connections of the rectifier Disconnect the Temperature Compensation Pro...

Page 12: ...ction Disconnect the Temperature Compensation Probe Connect an accurate voltmeter across the output Turn the mains on to the rectifier and adjust the variable voltage power supply up until the unit go...

Page 13: ...ature Compensation Probe Connect an accurate voltmeter across the output Turn AC and adjust the variable voltage power supply up until the alarm activates Adjust the Alarm Output High trimpot to adjus...

Page 14: ...P O Box 1306 Newport Beach California 92663 Phone 714 751 0488 Fax 714 957 1621 E Mail techservice newmarpower com 7 Dimensional Drawings 14...

Reviews: