New lift ADM 3 Manual Download Page 19

ADM-XK land call module

Technicaldata

ADMmanual

15

ADM-XK land call module

The ADM-XK controls the connected landing call panels via the control cables connected to X1. The ADM-XK 

is installed once in the control system and, from there, controls the buttons and directional displays for up to 14 

floors (2 buttons).

6.1 

Technical data

Description

Value

Supply voltage

24 V DC ±10%

Typical power consumption

50 mA

Outputs

Short circuit-proof

Length x height x depth

72 x 144 x 15 mm

Temperature range: Storage & transport / operation

-20 – +70 °C /   ±0 – +60 °C

Relative humidity: Storage & transport / operation 

(non-condensing)

 +5 – +95 % / +15 – +85 %

X1

X21

X22

J0

J1

J2

J3

J4

K1

K3

K2

72

6

144

72

7

137

Fig. 5.1: ADM-XK circuit board marking

6.2 

Installation and wiring

The ADM-XK can be installed in the control cabinet and fixed in place there with threaded bolts. As an alter-

native, it can also be mounted in a suitable housing outside the control cabinet. The wiring of the landing call 

panels is carried out locally during on-site installation.
The ADM-XK is connected to the shaft bus (FST X5 and X6) and supplied via the FST X4 (X4.1: +24 V, X4.2: 

GND).

Summary of Contents for ADM 3

Page 1: ...Landing call modules MANUAL J1 Service J1 Service...

Page 2: ...2 Doc no hb_adm_2015 12_en Copyright NEW LIFT Steuerungsbau GmbH 2015 This manual is protected by copyright All rights including those of copying of reproduction of translation and of modification in...

Page 3: ...call module 5 3 1 Technical data 5 3 2 Terminal assignment and configuration 5 3 2 1 Bus connection X1 X2 5 3 2 2 Jumper 6 3 2 3 Terminal strip 6 3 2 4 LED and micro fuse 7 4 ADM M land call modul 8...

Page 4: ...ata 15 6 2 Installation and wiring 15 6 3 Terminal assignment and configuration 16 6 3 1 Bus connection X21 X22 16 6 3 2 Terminal strip X1 16 6 3 3 Jumpers 16 6 3 4 Floor and door side assignment 17 6...

Page 5: ...eviations for detailed information in the case of terminals P Power I Input O Output L Low active H High active Information notice This symbol is located in front of relevant information 1 2 Further i...

Page 6: ...r the installation maintenance and commissioning of lift systems ZH 1 312 1 4 2 Electromagnetic compatibility EMC An accredited inspection authority has inspected the FST control system and its compon...

Page 7: ...re either installed and pre wired in the landing call panel or delivered loose to be ins talled in the shaft 2 1 Technical data Description Value Supply voltage 24 V DC 10 Typical power consumption 50...

Page 8: ...ll fire recall selective fire recall reset landing prio landing prio selective landing prio super remote shutdown remote shut down selective smoke alarm soft switch I L 14 Floor position 4 landing pri...

Page 9: ...2 additional connections X3 0 and X3 21 The ADM 3 is either installed and pre wired in the landing call panel or delivered loose to be installed in the shaft 3 1 Technical data Description Value Suppl...

Page 10: ...reset landing prio landing prio selective landing prio super remote shutdown remote shut down selective smoke alarm soft switch Key switch 1 fire recall fire recall selective fire recall reset landin...

Page 11: ...gured in the FST menu as a direction of travel output or a travel continuation output The terminals labelled with key switches 1 and 2 can be set at the factory with the functions fire recall smoke al...

Page 12: ...s contact area sunken red LED between X1 and X2 sunken green LED between X1 and X2 micro fuse 250 mA between X1 and X2 additional connection of key switch acoustic click etc on the terminal strip X6 T...

Page 13: ...2 3 Terminal strip ADM M X6 Standard Programming X6 11 GND X6 12 Key switch 1 fire recall fire recall selective fire recall reset landing prio landing prio selective landing prio super remote shutdown...

Page 14: ...at the factory The Direction func tion can be configured in the FST menu as a direction of travel output or a travel continuation output The terminals labelled with key switches 1 and 2 can be set at...

Page 15: ...x depth 72 x 144 x 15 mm Temperature range Storage transport operation 20 70 C 0 60 C Relative humidity Storage transport operation non condensing 5 95 15 85 K1 K3 K2 X21 X14 X13 X12 X11 X10 X9 X8 X7...

Page 16: ...r ADMX landing call 43 m 50 08018 47 m Ribbon cable for ADMX landing call 47 m 5 3 Terminal assignment and configuration 14 x 25 mA or 350 mA in total 14 x 40 mA or 560 mA in total 5 3 1 Bus connectio...

Page 17: ...lugged 1111 5 3 4 Floor and door side assignment The following configurations can be selected by setting jumpers J1 J4 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 26 25 27 28 29 3...

Page 18: ...010 Lift with 12 floors only one door side 0000 Lift with 10 floors bottom 4 floors at door B TG 0100 or 1010 Lift with 7 floors 2nd and 3rd floor at door B storage 1000 1001 or 1010 Lift with 23 floo...

Page 19: ...depth 72 x 144 x 15 mm Temperature range Storage transport operation 20 70 C 0 60 C Relative humidity Storage transport operation non condensing 5 95 15 85 X1 X21 X22 J0 J1 J2 J3 J4 K1 K3 K2 72 6 144...

Page 20: ...nding call 00 DOWN I O L 250 mA 24V 29 31 53 Landing call 01 UP landing call 02 UP landing call 13 UP I O L 250 mA 24V 30 32 54 Landing call 01 DOWN landing call 02 DOWN landing call 13 DOWN I O L 250...

Page 21: ...switch inputs Two freely configurable functions can be programmed for the key switches Here the input function for terminal X1 8 is configured via I O port 70 and the input function for terminal X1 4...

Page 22: ...Notes...

Page 23: ......

Page 24: ...NEW LIFT Steuerungsbau GmbH Lochhamer Schlag 8 82166 Graefelfing Tel 49 89 898 66 0 Fax 49 89 898 66 300 Mail info newlift de Service line Tel 49 89 898 66 110 Mail service newlift de www newlift de...

Reviews: