4. Chassis Resistance Measurement:
See Figure 2. Set the Polarity Switch to the OFF (center) position. Press the key
marked “CHS RES”. Plug the DUT into the test receptacle. Using the 503 test lead,
connect the chassis of the DUT to the CHASSIS jack on the LKG 610. The display will
present the Cord Resistance in milliohms.
Hammer pressure levels in excess of 20 PSI will cause damage t
Figure 2
Block Diagram for Cord Resistance measurement and
Case Leakage measurement (external)
5. Leads Leakage Measurement:
Leakage current of ECG leads may be measured individually or combined. To measure
the leakage press the appropriate function key LA, RA, RL, LEADS ALL, LL, or V1-V6.
The display will present the selected test measurement result in
µ
Amps.
Device Under
Test
DUT Power Cord
Test
Lead
(503)
to
Chassis