E-CODER
®
)R450
i™
Installation and Maintenance Guide
11
Chapter 5: Activating and Testing the E-CODER
®
)R450
i
™
This chapter defines how to read and test the E-CODER
®
)R450
i
™ to identify water leaks.
Activating the LCD Using the Solar Panel
Complete the following steps to activate and test the E-CODER.
1. Position the magnet over the magnetic area on the E-CODER, as shown, starting at the
bottom of the register box bringing the magnet up toward the top.
During the 30 seconds before the configuration transmission, the E-CODER)R450
i
acquires
the strongest R450™ Data Collector (R450 DC) for that location.
Figure 8 – Activating Using a Magnet
2. The E-CODER)R450
i
transmits its configuration packet to the collector approximately 30
seconds following the magnet swipe.
3. The E-CODER sends the register reading to the collector approximately 15 seconds
following the configuration packet.
Summary of Contents for E-CODER) R450i
Page 1: ...E CODER R450i Installation and Maintenance Guide...
Page 2: ......
Page 3: ...E CODER R450i Installation and Maintenance Guide...
Page 10: ...This page intentionally left blank ix E CODER R450i Installation and Maintenance Guide Figures...
Page 12: ...This page intentionally left blank xi E CODER R450i Installation and Maintenance Guide Tables...
Page 39: ......