STAND-OFF POSITIONING
8 o'clock
4 o'clock
Section View A A
(recommend installing at the
4 or 8 o'clock positions.)
!
Do not place pipe clamps
over the heater cable.
WARNING:
Stand-off
Fiberglass Tape
Sealing Grommet
Pipe Clamps
Box Adapter
not included in kit
Fiberglass Tape
254mm (10")
A
A
Stand-off
not included in kit
Mark pipe where stand-off will be mounted. See drawing above.
Push heater cable through bottom opening of stand-off.
Place stand-off on pipe and fasten with pipe clamps included.
Slide the sealing grommet over the heater cable and position inside stand-off opening:
For Braided “CB” Products only:
See
“Sealing Grommet Installation for Braided “CB” Products”
on
sheet 3.
Apply silicone around the heater cable on top of the sealing grommet and fill any voids in sealing grommet.
Slide the box adapter over the heater cable and tighten securely to stand-off.
Prepare heater cable for power termination:
for Braided “CB” Products, see sheet 3.
for Overjacket “J” or “JT” Products, see sheet 4.
Terminate heater cable, see sheet 7.
P.O. BOX 726 TULSA, OK 74101 TEL 918-627-5530 FAX 918-641-7336 www.nelsonheaters.com