GV20/GV15 INSTALLATION MANUAL
PREPARING FOR INSTALLATION
VERSION 5.0 2021-03-01
PAGE 2.1.1
SECTION 2.1: PREPARING FOR INSTALLATION
Before installing your GV20/GV15 transmitter, perform the following steps:
1.
Ensure that you have performed the pre-installation tasks described in the
GV20/GV15 Pre-installation Manual.
2.
Make sure that you received all the components. Check your packing list.
3.
Inspect all crates and packages for damage. Monitor the tip and drop indicators attached to the
crates to determine if a crate has been tipped over or has been subjected to excessive shock (see
Figure 2.1.1: Tip and drop indicators
4.
Report any damage immediately to your Nautel sales representative and the carrier.
5.
Move the crates as close as possible to the transmitter’s planned location.
6.
Unpack the crates in accordance with the instructions provided on the outside of the crates.
For each crate, remove the panel labelled
open this side
. The panel is attached using Phillips
head screws.
Remove any visible packing material, including braces, from the crate's interior.
Remove the lag bolts on the bottom edge of the remaining three sides, leaving only the
transmitter and its support pallet.
Summary of Contents for GV20
Page 2: ......
Page 4: ......
Page 8: ...GV20 GV15 INSTALLATION MANUAL PAGE 2 VIII VERSION 5 0 2021 03 01...
Page 18: ...GV20 GV15 INSTALLATION MANUAL UNPACKING AND POSITIONING PAGE 2 2 8 VERSION 5 0 2021 03 01...
Page 24: ...GV20 GV15 INSTALLATION MANUAL INSTALLING OPTIONS PAGE 2 3 6 VERSION 5 0 2021 03 01...
Page 36: ...GV20 GV15 INSTALLATION MANUAL INSTALLING PROGRAM INPUTS PAGE 2 7 4 VERSION 5 0 2021 03 01...
Page 50: ...GV20 GV15 INSTALLATION MANUAL COMMISSIONING PAGE 2 9 8 VERSION 5 0 2021 03 01...
Page 54: ...GV20 GV15 INSTALLATION MANUAL PARTS AND TOOLS PAGE 2 10 4 VERSION 5 0 2021 03 01...
Page 64: ...GV20 GV15 INSTALLATION MANUAL LIST OF TERMS PAGE 2 12 2 VERSION 5 0 2021 03 01...
Page 65: ......