4.2.9
The proper wiring route from main power supply to the parking lift is good for easier installation and
long-term usage. Make sure all wires are connected correctly and protected well.
4.2.10
Draw up positions of the post baseplates with chalk with less than 3mm tolerance.
4.2.11
Check carefully to make sure the layout is correct.
4.3 Necessary tools
4.4 Foundation treatment
4.4.1
Concrete ground with minimum 150mm depth is essential to install the parking lift. The concrete grade
should be at least C30.
For reinforced concrete, the foundation thickness should be at least 100mm.
4.4.2
Pour concrete above rammed earth at the base of posts as shown in below diagram.
4.4.3
Pre-embedded of anchor bolts is not needed.
(8) Foundation diagram
1 set of non-adjustable spanner, adjustable
spanner and allen wrench.
1 set of screwdriver (including slotted screwdriver
and phillips screwdriver)
1 piece of leveling instrument for 1M and 3M.
1 unit of forklift with 2T capacity.
1 piece of percussion drilling with 12x200 aiguille.
Insulated rubber tape
Sealing tape
1 electric welding machine
1 cutting machine
1 piece of electric portable drill
Some power line
1 piece of hammer
Some duster cloth
1 piece of grease gun
1 piece of tapeline for 5M