5 Installation and commissioning
41
BA5831400-00 EN
5.4.1.1.1 Wiring requirement of installation site
Note the following when selecting the installation site:
▪ The system's overvoltage protection must be effective.
▪ The system's ground connection must comply with all technical regula-
tions.
▪ Separate system parts must be joined by a potential equalization.
5.4.1.1.2 Wiring requirement of operating site
Note the following when wiring the operating site:
▪ Do not route lines which cause interference (e.g. supply lines) and lines
susceptible to interference (e.g. signal lines) in the same cable duct.
▪ Maintain a distance of more than 100 mm (3.94") between lines which
cause interference and those which are susceptible to interference.
Figure 21: Recommended wiring
1 Cable duct for lines causing inter-
ference
3 Cable duct for lines susceptible to
interference
2 Line causing interference (e.g.
power line)
4 Line susceptible to interference
(e.g. signal line)
▪ Never connect the device with a multi-wire collective pipe.
▪ Use a shielded cable for transmitting the output signal.
Summary of Contents for MESSKO MT-ST Compact
Page 25: ...3 Product description 25 BA5831400 00 EN 3 6 Nameplate Figure 9 Nameplate ...
Page 78: ...8 Disposal 78 BA5831400 00 EN Observe the national disposal regulations in the country of use ...
Page 90: ...10 Appendix 90 BA5831400 00 EN NPT adapters optional Figure 73 NPT adapters 1 2 NPT 3 4 NPT ...
Page 91: ......