6.3.2 Power Harness Installation
CDR kit contains power cable, circuit breaker, twist lock plug, and all necessary
connectors.
1. Route supplied power harness and hardware into machine electrical panel.
•
Be sure to leave enough cable leading outside the machine for twist lock plug to
reach CDR electrical panel.
•
If ¾” conduit plug is not available, knock out hole and use supplied cord grip.
2. Following local electrical codes, install 3phase power to 208-230VAC line (480V
optional).
•
The CDR is phased Red, White, Black.
•
Wire power cable in parallel with machine tool power.
•
Be sure to leave enough cable to properly ground the unit.
3. Locate proper grounding point. Attach using supplied ring terminals.
4. Connect twist lock plug into receptable on bottom of CDR electrical panel.
*Warning, pump may auto start when CDR disconnect is turned on*
3 phase power installation should only be performed by qualified
personnel.